Blog
1.2GW Big Rooter solar project breaks ground near Aggieland
- October 10, 2026
- Posted by: Clean Energy Skills
- Category: Solar Energy

Estimated reading time: 5 minutes · Last updated:
Construction is underway on Big Rooter Power, a $1.7 billion solar-and-storage development being built beside the Twin Oaks coal plant in Robertson County. Panamint Capital plans a 1.2-gigawatt array across nearly 10,000 acres using about 2 million panels, paired with a 1.6-gigawatt-hour battery and more than 20 miles of new transmission to feed ERCOT. The developer says the western half will go online in August 2028 and the eastern half the following year; the site also reserves 790 megawatts for a possible data center that Panamint says could open within five years. Project plans and contract figures were, as first reported by KBTX News 3, disclosed in county documents and developer statements.
“It’s important that as developers that we’re out there building these solar generation facilities now in order for us to make sure that we keep the cost low,”
Julia Olguin, Panamint Capital Chief Operating Officer
Key takeaways
- Panamint Capital is building the $1.7 billion Big Rooter Power project: a 1.2-gigawatt solar farm on nearly 10,000 acres adjacent to the Twin Oaks Power Plant.
- The development includes a 1.6-gigawatt-hour battery, more than 20 miles of transmission lines and about 2 million panels, and reserves 790 megawatts for a potential data center.
- The build will create about 800 temporary construction jobs, while the tax-abatement contract requires only four full-time positions and a $200,000 road deposit.
- Robertson County approved a 10-year, 100% property tax abatement under Chapter 312 that guarantees just over $13 million versus an estimated $25–30 million in standard taxes.
Table of contents
- Key takeaways
- How the project is built onto an existing coal site
- Timeline, capacity and the data center option
- Local opposition, property impacts and workforce numbers
- The county’s tax deal and the fiscal trade-offs
- What could push the project forward or slow it
- What to be careful about
- Frequently asked questions
How the project is built onto an existing coal site
Panamint Capital is integrating the 1.2-gigawatt solar array directly alongside the existing 310-megawatt Twin Oaks coal plant rather than siting the panels on undeveloped land. The developer says using reclaimed mine and plant property reduces additional environmental disturbance and lets the new output tie straight into ERCOT through on-site transmission.
Panamint plans roughly 2 million photovoltaic panels and a 1.6-gigawatt-hour battery facility to store generation for evening demand. Panamint said that, together with the coal plant, combined output would reach about 1.5 gigawatts — an amount that Panamint and county officials say could power at least 300,000 homes. The company also set aside 790 megawatts of capacity that could serve a future data center.
Timeline, capacity and the data center option
Panamint told county officials the western portion of Big Rooter is scheduled to start commercial operations in August 2028, with the eastern portion finishing in 2029 according to the company's timeline filed with the county.
Separately, Panamint has not committed to a data center but reserves 790 megawatts for one and said it is conducting evaluations of ways a data center could be colocated. Panamint told the county a data center could open within five years; county leaders are preparing for that possibility even though no partner or timeline has been confirmed in writing.
Local opposition, property impacts and workforce numbers
Several nearby landowners say the scale of the project will change the county’s rural character. Shane Bonnin, who bought 50 acres about three years ago, described the first row of panels being placed roughly 150 feet from a neighbour’s front door and said buyers have withdrawn offers after learning of the development. Panamint has agreed to remove a construction entrance and to plant vegetation buffers but declined to buy affected homes.
On jobs, Panamint projects about 800 temporary construction roles for the build phase, while long-term operations will be minimal: the tax-abatement contract obtained by KBTX requires only four full-time jobs, and the company estimated daily staff at around five to ten people to manage the facility.
The county’s tax deal and the fiscal trade-offs
Robertson County approved a 10-year, 100% tax abatement under Chapter 312 that applies to new equipment at the Big Rooter site. In exchange, Panamint agreed to make annual payments in lieu of taxes (PILOTs) and a $200,000 road deposit; the contract guarantees just over $13 million to the county over ten years.
County estimates filed with the county place unabated property-tax revenue at between $25 million and $30 million over the same decade. Those figures leave a projected revenue shortfall of roughly $6 million to $11 million compared with standard taxation, though the agreement notes the guaranteed payment could increase toward $17 million, with roughly $2 million more from land taxes — about $19 million in total if operations scale up. County Judge Joe David Scarpinato told the board the project would have come regardless, and that the deal was negotiated to secure budget predictability and avoid appraisal fights.
What could push the project forward or slow it
The case for
- Existing plant infrastructure and reclaimed mine land speed permitting and reduce the need to acquire undisturbed acreage, lowering siting friction.
- A reserved 790 megawatts for a data center would attract large power customers and raise long-term site revenues if a tenant signs on.
The case against
- Local opposition and visual-impact concerns may prompt legal challenges or force costly mitigation that Panamint has not committed to in writing.
- The county’s modest operational job requirement and the revenue gap from the tax abatement could fuel political pressure to reopen terms or seek state-level changes to Chapter 312 incentives.
What to be careful about
- County fiscal exposure: the PILOT guarantee of just over $13 million over ten years versus an estimated $25–30 million in standard taxes creates a $6 million to $11 million revenue shortfall if the higher valuation would have prevailed.
- Community and permitting risk from landowners who say pockets of the project sit very close to homes, increasing the chance of litigation or added mitigation costs.
- Commercial risk that a planned data center will not materialize despite the 790-megawatt reservation, leaving anticipated demand and tax upside unrealised.
The bottom line
Big Rooter Power is among the largest projects sited next to an operating coal plant in North America, and its scale brings clear benefits and tangible trade-offs. The project adds 1.2 gigawatts of solar, a 1.6-gigawatt-hour battery and transmission capacity to ERCOT, while the county accepted a 10-year, 100% equipment tax abatement that guarantees just over $13 million in PILOTs instead of an estimated $25–30 million in standard taxes. For residents the immediate issues are visual impact, dust and long-term land use; for officials the questions are whether written mitigation commitments and any future data center deal will meaningfully change the fiscal and community outcome.
What to watch
- Watch for Big Rooter West to begin commercial operations in August 2028.
- Watch for Big Rooter East to finish construction in 2029.
- Watch for Panamint Capital to announce whether a data center will proceed; the company says it could open within five years but has given no firm date.
Frequently asked questions
What exactly is being built at the Twin Oaks site?
Panamint Capital is building the Big Rooter Power project: a 1.2-gigawatt solar farm across nearly 10,000 acres with about 2 million panels, plus a 1.6-gigawatt-hour battery and more than 20 miles of transmission lines to feed ERCOT.
How many jobs and what tax deal came with the project?
The developer expects roughly 800 temporary construction jobs. The county’s Chapter 312 agreement requires four full-time positions and a $200,000 road deposit, and guarantees just over $13 million in PILOT payments over ten years versus an estimated $25–30 million if standard property taxes applied.
Will the coal plant close once the solar farm is online?
There is no firm closure plan in the public record; the Twin Oaks coal plant’s 310-megawatt unit is expected to operate in tandem with the new solar output for now, producing a combined roughly 1.5 gigawatts of capacity that Panamint and county officials say can serve at least 300,000 homes.
Related reading