SRP Drains Canyon Lake to Service Mormon Flat Dam
- October 19, 2026
- Posted by: Clean Energy Skills
- Category: hydropower

Estimated reading time: 4 minutes · Last updated:
The Canyon Lake drawdown is an SRP maintenance operation that opened Mormon Flat Dam’s 50-foot-tall gates so crews can sandblast and repaint flood-gate surfaces that have been underwater for 20 years. Salt River Project started lowering the reservoir in a 16-week programme; the four-week discharge that began on Sept. 16 completed the gate climb on Oct. 14 and left the lake 54 feet lower. SRP says the water released ran through the dam’s turbines to serve Phoenix-area households, and the company estimates the full sequence will finish by mid-January, Shi En Kim reported, as first reported by The Arizona Republic.
When we have a big storm come through, these gates need to operate flawlessly.
Matt Pendergraft, SRP’s director of hydro generation
Key takeaways
- Gate operation: SRP opened Mormon Flat Dam’s 50-foot-tall spill gates, which completed their full 50-foot climb on Oct. 14.
- Drawdown depth: Canyon Lake receded by 54 feet during the drawdown that began with a lake closure on Sept. 8.
- Reservoir size: Canyon Lake holds over 57,000 acre-feet — about 18.6 billion gallons, enough for roughly 171,000 families for a year.
- Timeline and schedule: SRP set a 16-week plan: four weeks to discharge and lower the lake, eight weeks for gate inspection and maintenance, and four weeks to refill starting in December.
Table of contents
Why SRP drained Canyon Lake and raised the gates
Salt River Project lowered Canyon Lake so crews could expose the flood gates at Mormon Flat Dam for a scheduled inspection and maintenance routine that SRP performs every 20 years on Bureau of Reclamation recommendations. The two submerged, stationary flood gates are normally underwater and protect downstream Saguaro Lake during high flows; after two decades sitting wet their steel faces become prone to rust and could seize if left unaddressed.
SRP director of hydro generation Matt Pendergraft described the work as essential for safety and reliability: “When we have a big storm come through, these gates need to operate flawlessly.” To access the gate faces, crews discharged water through the dam’s outlet and used heavy chains to raise the steel slabs once levels dropped below the gate sills.
How the water and power were managed during the drawdown
SRP routed the lake’s released water through the hydroelectric outlet over four weeks starting on Sept. 16, deliberately timing the work for fall when regional electricity demand is lower. While the lake level fell, Mormon Flat’s turbines were used to capture energy from the outflow so the release supplied households in the Phoenix metro area rather than being wasted.
Canyon Lake’s stated storage is over 57,000 acre-feet, or about 18.6 billion gallons; SRP says that volume is roughly equivalent to the annual supply for about 171,000 families. SRP also planned to move some water into other reservoirs on the Salt River system, including Apache and Roosevelt Lakes upstream, to refill Canyon Lake after maintenance.
Timeline, staffing and what happens next
SRP described the operation as a 16-week sequence: four weeks to lower the lake and expose gates, eight weeks for detailed inspection and off-site hydraulic repairs, then four weeks to refill starting in December, with the whole sequence expected to finish by mid-January. Canyon Lake had been closed to recreation since Sept. 8 to keep the public off exposed lakebed and around work zones.
The gate opening itself attracted retired hydro-generation specialist John Blevins back as a consultant; Blevins began at SRP in 1986 and retired in 2019, and he said the work drew him out of retirement because it is uncommon. SRP added that Horse Mesa Dam on Apache Lake will follow the same maintenance sequence, but no date for that drawdown has been set.
| Item | Figure or date | Source detail |
|---|---|---|
| Spill-gate height | 50-foot climb | SRP operation completed Oct. 14 |
| Drawdown depth | 54 feet | Observed lake recession during discharge |
| Reservoir capacity | Over 57,000 acre-feet (18.6 billion gallons) | Canyon Lake storage figure |
| Gate weight | Two 400,000-pound submerged gates | Equipment description in reporting |
How this maintenance could affect river operations
The case for
- Refurbished gates lower the risk of stuck barriers in heavy storms, improving flood control and operational resilience at Mormon Flat Dam.
- Using the released flow to turn turbines recovers energy for Phoenix-area households, reducing waste during routine maintenance.
The case against
- If crews find additional damage, SRP warned the sequence could extend beyond the planned mid-January finish, delaying refill and lengthening the period with no generation at Mormon Flat.
- Longer closures reduce public access and concentrate recreational use at other Salt River reservoirs, raising pressure on managers and local services.
What to be careful about
- Unplanned repairs discovered during gate inspection could extend the eight-week maintenance window and delay the refill now scheduled to take four weeks starting in December.
- Mormon Flat will not generate hydropower while the lake is lowered, making SRP rely on other resources to meet demand during the maintenance window.
The bottom line
SRP’s Canyon Lake drawdown was a planned, cyclical maintenance action to expose and refurbish two large flood gates that have remained underwater for 20 years. The company captured energy from the controlled release to serve households, closed the lake to the public for safety, and set a 16-week sequence that includes off-site hydraulic repairs and a planned refill window starting in December with a mid-January finish. The principal remaining uncertainties are whether inspections reveal extra repairs and the date for a similar sequence at Horse Mesa Dam; SRP has named staff and a timeline it can update if needed.
What to watch
- Watch for the four-week refill to start in December; no year is specified in the reporting.
- Watch for SRP updates on the eight-week gate inspection window and any additional repairs discovered; no firm public date for completion beyond mid-January has been given.
Frequently asked questions
Why did SRP lower Canyon Lake now?
SRP timed a 16-week maintenance sequence for the fall to lower water demand and to expose Mormon Flat Dam’s spill gates for sandblasting and painting; the gates are inspected every 20 years per Bureau of Reclamation recommendations.
How much water does Canyon Lake hold?
Canyon Lake stores over 57,000 acre-feet of water, equivalent to about 18.6 billion gallons, which SRP says could supply roughly 171,000 families for one year.
When will the lake return to normal levels?
SRP scheduled eight weeks for gate inspection and repairs after the drawdown, then four weeks to refill starting in December, with the full sequence expected to finish by mid-January; SRP cautioned this depends on whether additional repairs are needed.