Blog
Peñoles Signs 20-Year Solar and Storage Deal With Atlas
- November 20, 2026
- Posted by: Clean Energy Skills
- Category: Solar Energy

Estimated reading time: 6 minutes · Last updated:
Peñoles, the Mexican mining group, has signed a 20-year contract under which Atlas Renewable Energy will build a solar plant with battery storage in Coahuila and sell its output to the miner. The Peñoles solar and storage deal rests on a 269MWp installation expected to deliver roughly 550GWh of electricity a year once it starts running, a milestone targeted for the first half of 2029. Peñoles is buying capacity and Clean Energy Certificates as well as power. The supply is expected to avoid around 244,000t of CO₂ equivalent each year. Atlas says the contract is its first renewable supply agreement with a private-sector buyer in Mexico.
Mexican industry needs to secure energy today to strengthen the economy and sustain growth in the decades ahead.
Camilo Serrano, country manager for Mexico, Atlas Renewable Energy
Key takeaways
- The contract: Peñoles and Atlas Renewable Energy have signed a 20-year renewable supply agreement covering a solar and battery storage project in the Mexican state of Coahuila.
- The plant: The 269MWp installation is expected to supply Peñoles with about 550GWh a year, with operations planned for the first half of 2029.
- The emissions case: The supply is expected to avoid around 244,000t of CO₂ equivalent a year, adding to a power mix that was 49.9% renewable in Peñoles' 2025 Sustainability Report.
- Atlas in Mexico: Atlas Renewable Energy says Peñoles is its first private-sector client for renewable supply in Mexico.
Table of contents
- Key takeaways
- What 269MWp and 550GWh a Year Buy Peñoles
- Why the Contract Bundles Certificates, Capacity and Batteries
- How Far the Deal Moves Peñoles Beyond 49.9% Renewable Power
- Atlas Uses Peñoles to Open Its Private Market in Mexico
- What could help or hold back the project
- What to be careful about
- Frequently asked questions
What 269MWp and 550GWh a Year Buy Peñoles
The contract runs for 20 years and covers a solar generation project paired with batteries in the Mexican state of Coahuila. Atlas Renewable Energy will develop the plant, which is rated at 269MWp. MWp, or megawatts peak, measures what the panels can produce under standard test conditions, not what they deliver in a typical hour.
Expected annual supply to Peñoles is approximately 550GWh. Dividing that by the peak rating gives about 2,045MWh for every MWp installed, a rough indicator of how hard the panels are expected to work. That ratio does not reveal how much of the energy will pass through the batteries before reaching the miner.
Commercial operation is planned for the first half of 2029. The deal terms released so far include no contract price, no battery size and no construction schedule. That leaves the 20-year term, the plant rating and the annual volume as the firm commercial details on the record.
Why the Contract Bundles Certificates, Capacity and Batteries
Peñoles is not buying electricity alone. The contracted package combines renewable energy, capacity and Clean Energy Certificates, known in Mexico as CELs. A CEL is a certificate that records clean generation, allowing the holder to show that part of its consumption came from low-carbon sources.
The companies present the bundle as giving Peñoles more room to manoeuvre in its operations and as a support for its long-term energy planning. Contracting capacity alongside energy suggests a buyer that cares about reliability as much as volume. A mine cannot simply pause its processing load when supply runs short.
Batteries carry the demand side of that argument. Storage is designed to help Peñoles manage its electricity demand, which is treated as important for energy-intensive industries such as mining. Solar output follows daylight, while an industrial load does not. A battery lets some daytime generation be held back and used later, smoothing what the plant can offer the buyer.
How Far the Deal Moves Peñoles Beyond 49.9% Renewable Power
Peñoles already draws a large share of its power from renewables. Its 2025 Sustainability Report put that share at 49.9% of the electricity it consumed. The Atlas contract is part of a strategy to make its northern Mexican operations more competitive on energy and to lift the renewable portion of its processes.
The expected climate benefit is around 244,000t of CO₂ equivalent avoided each year. Set against 550GWh of annual supply, that implies roughly 0.44t of CO₂ equivalent displaced per MWh. That ratio reflects how carbon-intensive the power being replaced is assumed to be.
The figures do not show what the renewable share will be once the plant runs. Peñoles' total electricity consumption is not given, so the 550GWh cannot be turned into a percentage. Any claim that the deal takes the miner well past half renewable power would be a guess until the company publishes its own number.
Atlas Uses Peñoles to Open Its Private Market in Mexico
According to Atlas, Peñoles is the first private-sector customer in Mexico to which it has agreed to supply renewable power. It frames the deal as one more in a series of long-term supply contracts it holds with large energy users across Latin America, whose client list spans mining, chemicals, metals, cement and technology.
Camilo Serrano, Atlas Renewable Energy's country manager for Mexico, said the contract demonstrates that Mexico's big industrial users can turn to solar combined with battery storage as an option able to compete on its merits. He went on to describe solar-plus-storage as a technology in which Atlas leads across Latin America. That leadership claim is Atlas's own and is not backed by any market figure. Serrano also thanked Peñoles for trusting Atlas to develop and deliver the project.
Atlas expects the development and construction work to bring jobs and training to Coahuila. It says it will emphasise local supply chains and regional economic development. No headcount or local spending figure has been attached to those expectations.
| Term | Detail | Stated by |
|---|---|---|
| Contract length | 20 years | Peñoles and Atlas |
| Location | Coahuila, Mexico | Peñoles and Atlas |
| Solar capacity | 269MWp with battery storage | Peñoles and Atlas |
| Annual supply | About 550GWh | Peñoles and Atlas |
| Start of operations | First half of 2029 | Peñoles and Atlas |
| Emissions avoided | About 244,000t CO₂e a year | Peñoles and Atlas |
| Products contracted | Energy, capacity and CELs | Peñoles and Atlas |
What could help or hold back the project
The case for
- Contracting capacity and storage alongside energy gives Peñoles some control over when it draws power, not just how much it buys.
- A 20-year term gives Atlas a long revenue horizon to finance a 269MWp build in Coahuila.
- Atlas plans to use the deal as a reference case for other large industrial buyers in Mexico.
The case against
- No power flows until the first half of 2029, leaving a long build period before Peñoles sees any supply.
- The battery size is undisclosed, so how much daytime solar can be shifted to other hours is unknown.
- Peñoles' total consumption is not given, so the deal's effect on its 49.9% renewable share cannot yet be measured.
What to be careful about
- A delay to the first-half-2029 start would push back both the 550GWh of supply and the 244,000t of avoided emissions.
- Without a published battery capacity, the demand-management benefit Peñoles is paying for cannot be judged.
- Atlas has no previous private-sector supply contract in Mexico to show how it performs for local industrial clients.
The bottom line
The Peñoles contract gives Atlas Renewable Energy a foothold with private industry in Mexico and gives the miner a 20-year source of solar power, capacity and Clean Energy Certificates from Coahuila. The headline figures are clear: 269MWp, about 550GWh a year, around 244,000t of CO₂ equivalent avoided annually, and a start in the first half of 2029. Several details that would let a reader judge the deal remain unpublished. These include the price, the battery size and how far the supply moves Peñoles beyond the 49.9% renewable share in its 2025 Sustainability Report. Until those appear, the deal is best read as a signed volume commitment whose economics and climate effect will only be tested once the plant runs.
What to watch
- Watch for the plant to start operating in the first half of 2029, the date Peñoles and Atlas have set for first supply.
- Watch for a construction start in Coahuila and for the battery capacity to be named; no date has been given for either.
- Watch for Peñoles to report how far the Atlas supply lifts its renewable share above 49.9%; no date has been set.
Frequently asked questions
When will the Peñoles solar plant in Coahuila start supplying power?
Operations are planned for the first half of 2029. The 269MWp plant is then expected to supply about 550GWh a year to Peñoles under a 20-year contract.
Who is Atlas Renewable Energy's head in Mexico?
Camilo Serrano is Atlas Renewable Energy's country manager for Mexico. In his view, the Peñoles contract proves that pairing solar with storage gives Mexico's large industries a choice that can hold its own against other sources.
Which industries does Atlas Renewable Energy supply in Latin America?
Atlas says its long-term supply contracts across Latin America cover large consumers in mining, chemicals, metals, cement and technology. Peñoles is its first private-sector renewable supply client in Mexico.
Why does a mining company need battery storage with solar power?
Mining is energy-intensive, and storage is meant to help Peñoles manage its electricity demand rather than depend on daylight output alone. The battery size for the Coahuila project has not been disclosed.
Related reading