Blog
Geo POWER Act Would Back $800M in New Geothermal Projects
- November 19, 2026
- Posted by: Clean Energy Skills
- Category: Geothermal Energy

Estimated reading time: 6 minutes · Last updated:
The Geo POWER Act (S. 4116), a bipartisan Senate bill, would authorize up to $800 million for a Department of Energy (DOE) program that funds geothermal power demonstrations in stages. Money would be released as projects hit agreed development milestones. Of that sum, $750 million would go to the projects themselves and $50 million to administration and oversight. The bill favours regions with little or no geothermal generation today, including sites on or near tribal lands, and it leans on enhanced geothermal systems that can work where hot rock lacks natural pathways for fluid. The Senate Energy and Natural Resources Committee has reported the measure, but no floor vote has been scheduled. An identical House version, H.R. 8437, has also been introduced.
Senate Bill 4116, the GeoPower Act I have with Senator Hickenlooper.
Sen. Steve Daines (R-MT), at the 16 September Senate Energy and Natural Resources Committee hearing
Key takeaways
- The money: S. 4116 would authorize $750 million for geothermal demonstration projects plus $50 million for administration and oversight, a total of $800 million.
- The conditions: Eligible projects must be able to generate at least 30 megawatts and attract private investment. DOE would release funds only as each project meets development milestones.
- The spread: DOE would have 180 days after enactment to launch the program. It would then have to back at least three projects in three states with three separate sponsors.
- The status: The Senate Energy and Natural Resources Committee reported the bill on 12 November. The Senate has not scheduled a vote, and the Congressional Research Service lists House bill H.R. 8437 as identical.
Table of contents
- Key takeaways
- How Milestone Funding Would Work Under S. 4116
- Why the Bill Aims Enhanced Geothermal at New Regions
- Who Is Behind the Geo POWER Act and How Far It Has Got
- Why Committee Approval Is Not the Same as Funding
- What Could Help or Hold Back the Geo POWER Act
- What to be careful about
- Frequently asked questions
How Milestone Funding Would Work Under S. 4116
The Geo POWER Act would create the Milestone-Based Geothermal Demonstration Program inside DOE. Developers would not get a lump sum at the start. The department would pay out in stages as each project shows technical and commercial progress, so a project that misses its targets would not unlock its next payment.
DOE would have 180 days after enactment to set the program up. It would then have to back a minimum of three demonstration projects, spread over three states and run by three different sponsors. That requirement stops the money from pooling in a single company or a single geology.
To qualify, a project must show it could produce 30 megawatts or more and that it can draw in private capital. The bill also funds research into lowering the financial risk of later geothermal developments. The goal is to let private lenders carry more of the load in future without leaning so heavily on federal support.
Why the Bill Aims Enhanced Geothermal at New Regions
Most existing US geothermal plants sit in the western states. The bill points its money elsewhere. It gives priority to regions that generate little or no geothermal electricity today, including projects on or near tribal lands.
Enhanced geothermal systems are the technology meant to make that possible. DOE describes them as a way to tap underground heat where the rock lacks the fractures and fluid flow a conventional plant depends on. Developers create or improve channels for water to circulate through hot rock. In principle, that opens up a much wider set of sites.
Geothermal's main selling point is steadiness. Unlike solar and wind, a geothermal plant can run day and night whatever the weather. The obstacle is upfront risk. Companies often pay for exploratory wells before they know whether the ground below can support commercial generation, and the milestone structure is designed to share that early exposure.
Who Is Behind the Geo POWER Act and How Far It Has Got
Sen. John Hickenlooper, a Colorado Democrat, introduced S. 4116 on 17 March. He had three original cosponsors: Republicans Steve Daines of Montana and John Curtis of Utah, and Democrat Alex Padilla of California.
The Senate Energy and Natural Resources Committee examined the bill at a 16 September hearing. At that session, Daines listed four bills that had his backing, and this measure was among them. He voted to advance it when the panel ordered it reported with an amendment on 30 September. The committee formally reported the bill on 12 November, which put it on the Senate Legislative Calendar.
After the committee acted, Hickenlooper's office said the amended bill would speed up geothermal technology and help bring reliable, cleaner power nationwide. The World Resources Institute issued a supportive statement on the day of introduction. It argued that federal money could expand geothermal output and strengthen the grid. The Congressional Research Service lists the Senate bill and its House companion, H.R. 8437, as identical.
Why Committee Approval Is Not the Same as Funding
Being reported out of committee is not the same as passing. S. 4116 can now be brought to the floor, but the Senate has set no date for a vote, and H.R. 8437 would still have to move through the House. Supporters describe the program as a route into new geothermal markets. Until both chambers act, it remains a proposal rather than a pipeline of projects.
A signed law would not settle the technical questions either. Enhanced geothermal still faces high drilling costs and uncertainty about what lies underground. It also has to prove it can run profitably at commercial scale. The demonstration program exists because that proof is still missing.
The 30 megawatt threshold signals that these are meant to be power plants, not bench tests. Each of the three or more required demonstrations would test whether enhanced systems can deliver electricity in places with no geothermal industry today. Those are exactly the places where geological uncertainty is greatest.
| Date | Step | Who |
|---|---|---|
| 17 March | Bill introduced; WRI statement of support | Sen. John Hickenlooper and three cosponsors; World Resources Institute |
| 16 September | Committee hearing | Senate Energy and Natural Resources Committee |
| 30 September | Ordered reported with an amendment | Senate Energy and Natural Resources Committee |
| 12 November | Reported; placed on Senate Legislative Calendar | Senate Energy and Natural Resources Committee |
| Not scheduled | Senate floor vote | Full Senate |
What Could Help or Hold Back the Geo POWER Act
The case for
- The sponsors include two Democrats and two Republicans, and the bill cleared committee with an amendment.
- Milestone-based payments limit federal exposure to projects that stall before proving progress.
- The requirement for three states and three sponsors spreads the technical bets across different geologies and companies.
- Funded research into reducing financial risk could make later projects easier to finance privately.
The case against
- The Senate has not scheduled a floor vote, and the House companion H.R. 8437 has not advanced.
- Enhanced geothermal has yet to show it can operate economically at commercial scale.
- Drilling costs and geological uncertainty are likely to be higher in regions with no existing geothermal production.
What to be careful about
- The bill could stall on the Senate Legislative Calendar, because no floor vote has been scheduled.
- Demonstration projects in regions without geothermal production face greater geological uncertainty than sites in established western fields.
- Projects may struggle to meet both the 30 megawatt potential and the private-investment requirement, which would limit the pool of eligible sponsors.
The bottom line
The Geo POWER Act bets that the hardest part of new geothermal is drilling the first wells in unfamiliar ground. It assumes that federal money released in stages can carry developers past that point. Its terms are specific: $800 million in total, at least three projects across three states, and a 30 megawatt minimum for each. The design ties payment to progress and spreads the bets across sponsors and regions. What it cannot do by itself is prove that enhanced geothermal works economically outside the areas where the industry already operates. The demonstrations are meant to supply that evidence. The immediate test is political. No Senate vote is on the schedule, and the identical House bill has yet to move.
What to watch
- Watch for the Senate to schedule a floor vote on S. 4116; no date has been set.
- Watch whether the House takes up its identical companion bill, H.R. 8437; no House action date has been announced.
- If the bill becomes law, DOE would have 180 days from enactment to launch the demonstration program; enactment has no date yet.
Frequently asked questions
Is there a House version of the Geo POWER Act?
Yes. H.R. 8437 has been introduced in the House, and the Congressional Research Service identifies it as identical to S. 4116. Neither chamber has scheduled a vote.
Would geothermal projects on tribal lands get priority under the Geo POWER Act?
The bill gives priority to projects in regions with little or no geothermal electricity, and it explicitly includes projects on or near tribal lands. They would still need the potential to generate at least 30 megawatts and to attract private investment.
Who supports the Geo POWER Act outside Congress?
The World Resources Institute praised the bill in a statement on 17 March, the day it was introduced. WRI argued that federal investment could expand geothermal generation and strengthen the electricity grid.
How much of the $800 million goes to actual projects?
Up to $750 million would fund demonstration projects. The remaining $50 million would cover DOE's administration and oversight of the program.