A study of bringing up to 500 MW of Laos hydropower into Singapore is the subject of a memorandum of understanding (MoU) between Tuas Power, the Singaporean energy group owned by China Huaneng Group, and two Laotian partners: Électricité du Laos (EDL) and Phongsupthavy Group (PTSG). EDL and PTSG would be the suppliers, over a term that could run from 5 to 15 years. Nothing binding exists yet: the MoU only commits the parties to explore terms. The plan matters because Singapore still relies on gas for most of its generating fleet and, despite years of cross-border groundwork, imports no electricity as of November 2026.
Key takeaways
- The deal: Tuas Power, a China Huaneng Group subsidiary, has an MoU with Électricité du Laos and Phongsupthavy Group to explore up to 500 MW of Laotian hydropower supply for Singapore.
- The ramp: Imports would start at 100 MW in the first contract year, reach 300 MW in the second and settle at 500 MW from the third, over a possible 5 to 15 year term.
- The grid today: That dataset puts Singapore's installed capacity at 12.7 GW at the end of 2025, with 86% gas-fired and 11% renewable.
- The precedent: Keppel Energy agreed in 2022 to import up to 100 MW of Laotian renewable power via LTMS-PIP, yet Singapore has not begun importing electricity.
Table of contents
How the 100, 300 and 500 MW Ramp Would Work
The proposed schedule builds up in three steps. Tuas Power could take 100 MW in the first contract year, rise to 300 MW in the second, and hold at 500 MW from year three onward.
That last level equals roughly 4% of Singapore's 12.7 GW of installed capacity at the end of 2025. The 500 MW figure describes supply capacity, not an annual energy volume. No start date for the first contract year has been made public.
Why Certificates Could Matter to Tuas Power's Customers
Renewable Energy Certificates (RECs) are tradable records proving that a unit of electricity came from a renewable source. If the arrangement goes ahead, Tuas Power could attach RECs to the Laotian hydropower it buys.
That pairing would give the company's customers the option of bundled renewable energy products. Renewables made up just 11% of Singapore's capacity at the end of 2025. The bundling remains conditional on the supply deal being concluded first.
Singapore Has an Import Framework but No Imports
Gas-fired plants made up 86% of Singapore's capacity at the end of 2025, according to Enerdata's Global Energy data. The grid has been linked to Peninsular Malaysia since 1983, and a Laos route already exists on paper.
In 2022, Keppel Energy contracted to bring in as much as 100 MW of Laotian renewable electricity via LTMS-PIP, a power integration project linking Lao PDR, Thailand, Malaysia and Singapore. Phase 2 of that project doubled trading capacity to 200 MW and opened multidirectional trade, adding scope for Malaysian supply.
The EMA extended Keppel's importer licence until 2026. Singapore is still importing no power.
| Arrangement | Year | Capacity | Status |
|---|---|---|---|
| Tuas Power with EDL and PTSG | 2026 | Up to 500 MW | MoU to explore terms |
| Keppel Energy via LTMS-PIP | 2022 | Up to 100 MW | Contract signed, no imports yet |
| LTMS-PIP Phase 2 | Not stated | 200 MW trading capacity | Multidirectional trade introduced |
What could help or stall the import plan
The case for
- A staged 100, 300, 500 MW ramp spreads the supply build-up over three contract years.
- Pairing the hydropower with RECs would give Tuas Power a bundled renewable product for customers.
- LTMS-PIP Phase 2 already doubled trading capacity to 200 MW and allows multidirectional trade.
The case against
- The MoU is exploratory and commits no party to supply or buy power.
- Keppel's 2022 contract has not yet produced any imports into Singapore.
- No timetable for a binding supply contract has been published.
What to be careful about
- The MoU may never become a binding supply agreement with EDL and PTSG.
- Delivery at 500 MW would far exceed the 200 MW trading capacity reached under LTMS-PIP Phase 2.
- Singapore's lack of any power imports to date shows cross-border plans can stall after signing.
The bottom line
The Tuas Power MoU follows Keppel Energy's earlier push to bring Laotian renewable power to Singapore, and targets five times the capacity. Keppel's 100 MW contract dates from 2022, yet Singapore still imports no electricity, a gap that shows how far a signed intent can sit from flowing power. Tuas Power, EDL and PTSG have published no timetable for turning their MoU into a binding supply contract. The MoU leaves the contract term open, anywhere from 5 to 15 years. Until they do, the 500 MW figure is an ambition rather than a commitment, and gas still dominates Singapore's generating fleet.
What to watch
- Keppel Energy's importer licence from the EMA runs until 2026, so watch whether it is extended again before that year closes.
- Watch for Tuas Power, EDL and PTSG to turn the MoU into a binding supply agreement; no date has been set.
Frequently asked questions
Who would supply the Laos hydropower to Singapore?
Électricité du Laos (EDL) and Phongsupthavy Group (PTSG) would be the suppliers under the arrangement Tuas Power is exploring. The volume could reach 500 MW from the third contract year.
Does Singapore import electricity from Laos today?
No. Keppel Energy signed a contract in 2022 for up to 100 MW of Laotian renewable power through LTMS-PIP, but Singapore has not yet started importing power.
Who owns Tuas Power?
Tuas Power is a Singaporean energy group and a subsidiary of China Huaneng Group. It signed the MoU with EDL and PTSG.
How long would the Laos supply deal last?
The proposed term could run from 5 to 15 years. That range is not final, because the MoU only commits the three parties to explore terms.