The US Department of Defense has roughly 400 onshore wind projects waiting for its clearance, and action on every one of them depends on eight federal employees. Dale Marks, the Pentagon's assistant secretary overseeing energy, installations, and environment, told a federal court in Oregon this in a 3 November filing. Marks said the review teams were never built for the recent surge in applications, and that they are working with less staff, money and contractor help. DOD also argued that it is obeying an August injunction and has restarted its reviews. The American Clean Power Association disputes that. It says no project has moved forward in substance, while developers keep paying to wait.
Despite the Court's clear orders, DOD has not resumed review.
Tom Vinson, American Clean Power Association
Key takeaways
- The queue: Dale Marks told the federal court in Oregon on 3 November that about 400 onshore wind projects are awaiting DOD action.
- The bottleneck: Marks said contractors cannot perform inherently governmental work, so decisions rest solely with eight federal employees across DOD.
- The workload: DOD typically signed 13 mitigation agreements a year, but Marks said the recent annual figure has hovered around 30.
- The dispute: Tom Vinson of the American Clean Power Association said in an 20 October declaration that DOD has not resumed substantive review despite the court's orders.
- The cost: Vinson cited one delayed project that could lose an Advanced Manufacturing Credit worth about $200,000 per turbine, or roughly $24 million in total, if equipment arrives after 31 December 2027.
Table of contents
Why the Pentagon Says Eight Staff Cannot Clear 400 Wind Projects
Marks' declaration describes a review office buried by volume. He wrote that none of DOD's wind review teams "are sized to manage the dramatic influx of applications received in recent years." That surge arrived while the department was also losing manning, funding and contractor support.
Outside help cannot fill the gap. Marks said contractors are barred from carrying out inherently governmental functions. That leaves decisions on the roughly 400 queued projects "solely" with eight federal employees spread across the department.
The office has already raised its output. "In an average year, the [DOD] would execute 13 mitigation agreements, but more recently, this number has hovered around 30," Marks said. A mitigation agreement sets out the steps a developer takes to limit a project's effect on military readiness.
The permits come from DOD's Military Aviation and Installation Assurance Siting Clearinghouse. The department says this office stopped pausing its processing work after the court stayed the freeze, and is now actively assessing projects.
Is DOD Actually Reviewing Wind Projects Again?
Tom Vinson rejects the Pentagon's account. He is vice president for policy and regulatory affairs at the American Clean Power Association (ACP). In a declaration dated 20 October, he drew partly on information from ACP members. "Despite the Court's clear orders, DOD has not resumed review," according to Vinson. He went on: "While it may have reported some administrative activity, none of this activity has resulted in any substantive movement through mitigation review."
The two sides are using different yardsticks. DOD points to assessment work under way. Vinson asks whether any project has actually advanced. The judge will have to decide which measure counts as compliance.
Vinson also testified that the delay is eroding project economics, because developers keep paying costs while they wait. He said one project's turbine delivery has slipped. He noted that "equipment delivered after December 31, 2027, will not qualify for the Advanced Manufacturing Credit." The developer puts that credit at approximately $200,000 per turbine, or roughly $24 million across that project.
How a Review Freeze Became a Federal Lawsuit
States, developers and clean energy industry trade associations joined together to take DOD to court. Their complaint, filed on 31 May, alleged that the department "stopped fulfilling its statutory mandate" to assess how wind projects affect military readiness. It said the process stalled after Marks was confirmed.
The plaintiffs asked the court to set aside the review freeze policy and to order DOD to act by fixed dates. In August, the court issued an injunction staying what DOD called a "temporary pause."
The plaintiffs later argued that DOD was ignoring the stay and asked the court to enforce it. DOD's 3 November response opposes that motion and says the department is complying. The plaintiffs must reply by 17 November. After that, the judge decides whether the Pentagon's renewed activity satisfies the order.
| Filing | Filed by | Date | Core claim |
|---|---|---|---|
| Original complaint | Trade groups, developers, states | 31 May | DOD stopped its statutory wind reviews |
| Declaration | Tom Vinson, ACP | 20 October | No substantive movement through mitigation review |
| Opposition to enforcement motion | DOD, Dale Marks | 3 November | Reviews resumed; about 400 projects, eight staff |
| Plaintiffs' reply | Plaintiffs | Due 17 November | Pending |
What could speed or stall the wind queue
The case for
- Marks said DOD has already lifted annual mitigation agreements from an average of 13 to around 30.
- The August injunction remains in force, and the court can press for compliance if it grants the enforcement motion.
The case against
- Marks said only eight federal employees can act on about 400 projects, and contractors cannot take on that work.
- Marks described continuing pressure on manning, funding and contractor support for the review teams.
- Vinson said turbines delivered after 31 December 2027 lose Advanced Manufacturing Credit eligibility, so each month of delay raises the stakes for developers.
What to be careful about
- Projects with slipping turbine deliveries could miss the 31 December 2027 cutoff for the Advanced Manufacturing Credit, losing about $200,000 per turbine on Vinson's example.
- Even with the court's backing, eight reviewers handling about 400 projects may keep throughput far below demand.
- The court could accept DOD's view that administrative activity counts as compliance, leaving developers without a firm timetable.
The bottom line
Marks' filing contains an unusual admission. Even a Pentagon that fully obeys the court has eight people to work through about 400 onshore wind projects. Higher output, from 13 mitigation agreements a year to around 30, does not close that gap. The live question for the judge is narrower: does renewed administrative activity count as complying with the August stay? ACP says it does not, because nothing has moved through mitigation review. For developers, the clock that matters is the 31 December 2027 cutoff for the Advanced Manufacturing Credit. The plaintiffs' 17 November reply is the next point where either side can show the court what has actually changed.
What to watch
- The plaintiffs' reply to DOD's opposition is due on 17 November and will show what evidence they offer that reviews remain stalled.
- Watch for the judge's ruling on the motion to enforce the stay; no date has been set.
- Watch whether delayed projects receive turbines before the 31 December 2027 cutoff for the Advanced Manufacturing Credit.
Frequently asked questions
Why does the Department of Defense review onshore wind projects?
The plaintiffs' complaint says DOD has a statutory mandate to assess how wind projects affect military readiness. Permits come from its Military Aviation and Installation Assurance Siting Clearinghouse.
Why can't the Pentagon hire contractors to clear the wind backlog?
Dale Marks said contractors cannot perform inherently governmental functions. As a result, action on about 400 projects rests solely with eight federal employees.
How could the delay affect wind project tax credits?
Tom Vinson said equipment delivered after 31 December 2027 will not qualify for the Advanced Manufacturing Credit. For one delayed project, the developer estimates the loss at about $200,000 per turbine, or roughly $24 million.
What happens next in the DOD wind lawsuit?
The plaintiffs must reply to DOD's 3 November filing by 17 November. The court will then rule on their motion to enforce the August stay.