POWERCHINA will build the 500 MW Ras Shukeir wind farm in Egypt's Red Sea Governorate for Amunet for Renewable Energy S.A.E, under an engineering, procurement and construction contract signed by the pair. An EPC contract puts one firm in charge of design, purchasing and building. AMEA Power, headquartered in the United Arab Emirates, is developing the project as an independent power producer and will operate it. The site lies roughly 15 km west of Ras Shukeir. It is the fourth Egyptian wind project POWERCHINA has taken on under the EPC model, bringing its contracted wind capacity in the country to 2.3 GW.
Key takeaways
- The contract: POWERCHINA signed an EPC contract with Amunet for Renewable Energy S.A.E to build the 500 MW Ras Shukeir wind farm in Egypt's Red Sea Governorate.
- The hardware: The Ras Shukeir design uses 45 turbines rated at 11 MW each across a 54 km site about 15 km west of Ras Shukeir.
- The output: Ras Shukeir is expected to generate more than 2.3 billion kWh a year, supply over 500,000 households and avoid about 940,000 tonnes of carbon dioxide annually.
- POWERCHINA in Egypt: Ras Shukeir is POWERCHINA's fourth EPC wind project in Egypt, taking its contracted wind capacity there to 2.3 GW.
Table of contents
What POWERCHINA Will Deliver at Ras Shukeir
POWERCHINA's remit runs past construction. Beyond the EPC work itself, the contractor will commission the plant, hand it over to the owner and provide warranty services afterwards. That leaves a single company accountable from the first foundation to the end of the warranty period.
The layout covers 54 km and is built around 45 large turbines, each rated at 11 MW. Multiplied out, those machines come to roughly 495 MW, a little short of the 500 MW total installed capacity quoted for the project. No explanation for the gap has been given.
Amunet for Renewable Energy S.A.E is the counterparty signing with POWERCHINA, while AMEA Power, as developer, will run the asset once built. No construction timetable has been published.
What 2.3 Billion kWh a Year Means for Egyptian Homes
Once running, the wind farm is expected to produce more than 2.3 billion kWh of electricity each year. That output is pegged to supplying over 500,000 households, which works out at roughly 4,600 kWh per home annually.
It is also expected to cut carbon dioxide emissions by around 940,000 tonnes a year. These are forecasts, not measured results; real generation will depend on wind conditions at the Red Sea site.
Egypt has set a goal of drawing 45% of its energy mix from clean sources by 2028, and Ras Shukeir is framed as a contribution to that target and to the country's emissions pledges under the Paris Agreement. Economic and social development and energy security are its other stated aims.
How Ras Shukeir Extends POWERCHINA's Run in Egypt
POWERCHINA and Amunet have worked together in Egypt's renewable sector before, and the new contract comes after the 500 MW Gulf of Suez wind farm was commissioned in May 2025. That earlier plant matches Ras Shukeir in headline size.
With this signing, POWERCHINA's contracted wind capacity in Egypt across its four EPC projects reaches 2.3 GW. Ras Shukeir's 500 MW makes up roughly 22% of that total, so the other three contracts account for about 1.8 GW between them.
The ownership structure explains how a builder can accumulate that much capacity. Under the independent power producer model, AMEA Power develops and operates the plant, while POWERCHINA's role ends with construction, commissioning, handover and warranty. The contractor builds; it does not own.
| Project | Capacity | Status | Key date |
|---|---|---|---|
| Gulf of Suez wind farm | 500 MW | Commissioned | May 2025 |
| Ras Shukeir wind farm | 500 MW | EPC contract signed | Not disclosed |
What could help or hold back Ras Shukeir
The case for
- A single contractor covering EPC, commissioning, handover and warranty reduces the number of handoffs between build and operation.
- Egypt's target of 45% clean energy by 2028 gives the project clear policy support.
- POWERCHINA has an existing working relationship with Amunet in Egypt, following the Gulf of Suez project commissioned in May 2025.
The case against
- No construction schedule has been published, so the plant's contribution to the 2028 target is uncertain.
- The 45 turbines at 11 MW each total about 495 MW, slightly below the 500 MW stated capacity, an unexplained discrepancy.
- Generation and household figures are projections that depend on how the site's wind resource performs in operation.
What to be careful about
- Construction timing is undisclosed, so the plant may not be producing in time to count toward Egypt's 2028 goal of 45% clean energy.
- The output estimate of more than 2.3 billion kWh a year is a forecast and could fall short if wind conditions at the Red Sea site underperform.
- Reliance on 11 MW turbines means a large share of capacity sits in each machine, so individual turbine outages remove more output.
The bottom line
Ras Shukeir follows the 500 MW Gulf of Suez farm commissioned in May 2025, and it lands as Egypt chases a 45% clean energy share by 2028. The plant's numbers are concrete: 45 turbines of 11 MW, more than 2.3 billion kWh a year for over 500,000 households and around 940,000 tonnes of carbon dioxide avoided annually. What remains open is timing. No start or completion date has been disclosed, so it is not yet clear whether the plant can contribute before that 2028 deadline. The small gap between turbine nameplate and stated capacity also deserves clarification from the companies involved.
What to watch
- Watch for a construction start date at Ras Shukeir; neither POWERCHINA nor AMEA Power has set one publicly.
- Egypt's 2028 deadline for clean energy to reach 45% of its energy mix is the yardstick for whether Ras Shukeir arrives in time to count.
- Look for the companies to reconcile the 45 turbines of 11 MW with the 500 MW stated capacity; no date has been set for any clarification.
Frequently asked questions
Who owns and operates the Ras Shukeir wind farm?
AMEA Power, which is headquartered in the United Arab Emirates, develops and will operate Ras Shukeir as an independent power producer. POWERCHINA builds the plant under an EPC contract signed with Amunet for Renewable Energy S.A.E.
How many turbines will Ras Shukeir use?
The project is designed around 45 wind turbines, each rated at 11 MW. Together those come to about 495 MW, slightly below the 500 MW total installed capacity given for the project.
How does Ras Shukeir help Egypt's clean energy goals?
Egypt aims for clean energy to make up 45% of its energy mix by 2028. Ras Shukeir is expected to avoid around 940,000 tonnes of carbon dioxide a year and supports the country's Paris Agreement commitments.