Italy Battery Storage Approvals Add 598 MW in Five Projects
- November 20, 2026
- Posted by: Clean Energy Skills
- Category: Battery storage

Estimated reading time: 6 minutes · Last updated:
Italy's Ministry of Environment and Energy Security (MASE) has signed off on five standalone battery energy storage systems with a combined 598.3 MW of power, in decrees numbered 338/2026 to 342/2026. The approvals went to companies tied to Zhero Group, Opdenergy, Neoen, Reden and Chiari Srl. The sites are in Sardinia, Lombardy, Brindisi, Benevento and Foggia. Two earlier approvals dated 2 November lift the ministry's November total for Italy battery storage authorizations to 1,078 MW. A standalone BESS is a battery plant that is not paired with a generator on the same site. Construction schedules across the five run from about nine months to around 24, so the batch will not come online together.
Key takeaways
- 598.3 MW approved: Italy's Ministry of Environment and Energy Security issued five decrees, numbered 338/2026 to 342/2026, for standalone batteries totaling 598.3 MW.
- Atena Storage in Sardinia: Zhero Group's 200 MW Atena Storage project in Selargius, Cagliari province, has a 12-month construction schedule under Decree 341/2026.
- Chiari storage duration: Chiari Srl's 151.2 MW system in Brescia province will use 200 containers holding about 688 MWh, a little over four and a half hours at full power.
- November total: With Miura Storage's 280 MW Tuscania project and the 200 MW Bess Castegnero project approved on 2 November, MASE authorized 1,078 MW in November.
- Build times diverge: Neoen's 97.92 MW Benevento battery has a schedule of about nine months, while Reden's 50 MW San Severo project expects around 24 months.
Table of contents
- Key takeaways
- What Zhero Group's 200 MW Selargius Approval Covers
- How 200 Containers Give the Chiari Battery About 4.5 Hours
- Two Fund-Owned Developers, Two Very Different Build Times
- Is Reden Building a Matched Pair in San Severo?
- How Seven November Approvals Reached 1,078 MW
- What could speed or slow the 598 MW batch
- What to be careful about
- Frequently asked questions
What Zhero Group's 200 MW Selargius Approval Covers
Atena Storage is a 200 MW battery planned for Selargius, in the Sardinian province of Cagliari. Its holder is Atena Storage Srl, a company based in Milan and owned by the Dutch developer Zhero Group. MASE granted the approval under Decree 341/2026.
At 200 MW, the project supplies about a third of the 598.3 MW in this round. The other four range from 50 MW to 151.2 MW, so this one Sardinian site outweighs each of the others on power.
The company has set a 12-month construction period. That is a plan rather than a delivery commitment: an authorization allows building to begin, and the published details give no start date. Nor do they give the project's energy capacity in megawatt-hours, so how many hours Atena Storage can discharge at full power is not yet public.
How 200 Containers Give the Chiari Battery About 4.5 Hours
In Lombardy, Chiari Srl, also headquartered in Milan, won Decree 339/2026 for a 151.2 MW system in the town that shares its name, Chiari, in Brescia province. Building is expected to last 10 months.
Power and energy are different measures. Megawatts describe how fast a battery can push electricity into the grid; megawatt-hours describe how much it holds. The Chiari plan uses 200 battery containers rated at 3.44 MWh apiece, which adds up to roughly 688 MWh.
Divide that energy by the 151.2 MW of power and the plant can run flat out for a little over four and a half hours. A longer duration lets a battery keep supplying power through more of a high-demand period instead of covering only a brief spike. The published details of the other four approvals carry no comparable energy figure, which makes Chiari the easiest of the five to assess.
Two Fund-Owned Developers, Two Very Different Build Times
Opdenergy, a Spanish developer controlled by the investment fund Antin Infrastructure Partners, holds the Brindisi approval through Opdenergy Italia 2 Srl. Its Greentuke BESS is rated at 99.165 MW and is covered by Decree 340/2026. The plant will be split into a northern and a southern section, and construction is planned to take around 600 days.
Neoen, the French developer controlled by Brookfield, secured Decree 342/2026 through Neoen Renewables Italia Srl. Its 97.92 MW battery sits in Benevento, in Campania, and is scheduled to be built in about nine months.
The two projects are almost the same size, yet their schedules sit far apart. Greentuke's 600-day estimate runs well past a year; Neoen's falls short of one. The published details do not explain the gap, though the two-part layout at Brindisi is one visible difference between them.
Is Reden Building a Matched Pair in San Severo?
Reden's subsidiary Electricity Time Shifting 3 Srl received Decree 338/2026 for a 50 MW battery in San Severo, Foggia province. Building is expected to take around 24 months, double the schedule set for Atena Storage.
The project looks like half of a pair. On 30 October, the ministry had already approved a 50 MW facility in the same municipality for Electricity Time Shifting 4 Srl. Identical size, the same town and consecutive company numbering all suggest a twin development, which would mean about 100 MW of approved storage across the two companies in San Severo.
That reading rests on names and numbers rather than on anything the decrees state. The published details do not say whether the two share an owner, a grid connection or a construction timetable, so the pairing should be treated as likely rather than settled.
How Seven November Approvals Reached 1,078 MW
The five decrees followed two earlier battery approvals in the same month. On 2 November, MASE cleared a 280 MW Miura Storage battery at Tuscania, Viterbo province. BESS Pieve Srl is behind the other, the 200 MW Bess Castegnero scheme in Castegnero Nanto, Vicenza province.
Added to the 598.3 MW in the latest batch, those two bring the capacity MASE authorized in November to 1,078 MW across seven projects. Miura Storage's 280 MW is larger than any single project in the newer group of five.
A ministerial authorization is a permit, not a working power plant. Each of these sites still has to be equipped and connected, and the build times quoted run from about nine months to around 24. The November figure therefore measures the pipeline cleared to proceed rather than capacity that will feed the grid this winter.
| Project holder | Developer | Location | Power (MW) | Decree | Build time |
|---|---|---|---|---|---|
| Atena Storage Srl | Zhero Group | Selargius, Cagliari | 200 | 341/2026 | 12 months |
| Chiari Srl | Chiari Srl | Chiari, Brescia | 151.2 | 339/2026 | 10 months |
| Opdenergy Italia 2 Srl (Greentuke) | Opdenergy | Brindisi | 99.165 | 340/2026 | About 600 days |
| Neoen Renewables Italia Srl | Neoen | Benevento | 97.92 | 342/2026 | About 9 months |
| Electricity Time Shifting 3 Srl | Reden | San Severo, Foggia | 50 | 338/2026 | About 24 months |
What could speed or slow the 598 MW batch
The case for
- Seven approvals in one month cleared 1,078 MW of standalone storage to proceed.
- Neoen's roughly nine-month and Chiari Srl's 10-month schedules mean part of the batch could be built within a year once work starts.
- Chiari's 688 MWh design gives a little over four and a half hours of discharge at full power.
The case against
- No construction start dates have been published for any of the five projects.
- Energy capacity in MWh has been published for Chiari but not for the other four, leaving their storage duration unknown.
- Greentuke's roughly 600-day and San Severo's roughly 24-month schedules push part of the capacity well beyond a year.
What to be careful about
- An authorization permits construction but does not guarantee it; none of the five projects has a published start date.
- Without MWh figures for Atena Storage, Greentuke, Benevento and San Severo, the batch's real storage contribution cannot be measured.
- The San Severo twin-project link is inferred from company names and sizes, not stated in the decrees.
The bottom line
November 2026 has been a busy month for Italy battery storage permitting. Seven standalone projects totaling 1,078 MW cleared MASE, and the five most recent decrees alone add 598.3 MW spread across Sardinia, Lombardy, Brindisi, Benevento and Foggia. The developers range from the Brookfield-controlled Neoen and the Antin-backed Opdenergy to Reden, Zhero Group and Milan-based Chiari Srl. What the approvals leave out matters as much as what they contain. The published details give energy capacity for Chiari but not for the other four, construction start dates are absent, and the possible pairing in San Severo rests on names rather than a stated link. The next useful signals will be work starting on site and MWh figures for the remaining projects.
What to watch
- Watch for a construction start at Neoen's Benevento site, where the approved build takes about nine months; no start date has been published.
- Watch for developers to disclose energy capacity in MWh for Atena Storage, Greentuke, Benevento and San Severo; none has been made public so far.
- Watch for any further MASE battery authorizations before the end of November 2026 that would add to the 1,078 MW monthly total; no schedule has been announced.
Frequently asked questions
Which Italian regions and provinces are getting the new battery projects?
The five latest approvals sit in Selargius in Cagliari province in Sardinia, Chiari in Brescia province in Lombardy, Brindisi, Benevento in Campania, and San Severo in Foggia province. The two approved on 2 November are in Tuscania in Viterbo province and Castegnero Nanto in Vicenza province.
How long will Italy's newly approved battery projects take to build?
Neoen's 97.92 MW Benevento project is scheduled for about nine months and Chiari Srl's 151.2 MW plant for 10 months. Atena Storage expects 12 months, Opdenergy's Greentuke around 600 days, and Reden's San Severo battery around 24 months.
Does a MASE authorization mean an Italian battery is already being built?
No. A single authorization from Italy's Ministry of Environment and Energy Security clears a project to proceed, but none of the five decrees issued in November 2026 comes with a published construction start date.