First Solar, Inc. has opened the first 1.7 GW phase of its module factory in Gaffney, Cherokee County, South Carolina. The plant is part of a $330 million investment that moves the last stages of photovoltaic module production from the company's overseas fleet onto US soil. A company release says the site should reach 3.4 GW of annual nameplate capacity when it is finished in mid-2027. The line produces Series 6 Plus modules, thin-film panels built from cadmium telluride rather than crystalline silicon and designed for utility-scale projects. Chief executive Mark Widmar opened the First Solar South Carolina plant at a ribbon-cutting ceremony. The company says the project is on track to support nearly 700 jobs, and about 500 have reportedly been filled.
Less than a year after we selected Gaffney, this facility is ready to produce American solar technology, built by South Carolinian workers.
Mark Widmar, CEO, First Solar
Key takeaways
- Phase one is running: First Solar's Gaffney, South Carolina factory opened its first 1.7 GW phase as part of a $330 million investment, and full 3.4 GW capacity is expected by mid-2027.
- Copper-free cell design: The Series 6 Plus cadmium telluride modules made at Gaffney deliver up to 480 watts each and use First Solar's CuRe technology, which replaces copper with Group V elements.
- Supply chain pitch: Mark Widmar, First Solar's CEO, says Gaffney modules have no dependence on Chinese crystalline silicon supply chains, while Wood Mackenzie flags FEOC-free sourcing as a possible bottleneck over the next two to four years.
- Jobs and national capacity: The project is on track to support nearly 700 jobs, about 500 reportedly already filled, and First Solar forecasts roughly 17 GW of US module capacity by the end of 2026.
Table of contents
- Key takeaways
- Why First Solar Is Finishing Modules in Gaffney
- How CuRe Replaces Copper in Cadmium Telluride Cells
- Is Domestic Thin Film a Hedge Against Supply Bottlenecks?
- Jobs and a Wider South Carolina Footprint
- What could help or hurt the Gaffney build
- What to be careful about
- Frequently asked questions
Why First Solar Is Finishing Modules in Gaffney
The Gaffney plant is a finishing operation. First Solar is using the $330 million to bring the final production steps for modules home from its international factories, so panels destined for American customers are completed in the United States.
The build is split in two. The 1.7 GW now operating is half of the 3.4 GW the company expects once the site is complete in mid-2027, which leaves about 1.7 GW still to come online over the next several months.
Speed is the point Widmar chose to stress at the ceremony. He said the plant was ready to produce less than a year after the company chose Gaffney, and he credited policy, state and local partners and the workforce for that pace. That timeline is the company's own account, and the second phase is still a forecast rather than a finished line.
How CuRe Replaces Copper in Cadmium Telluride Cells
Cadmium telluride, or CdTe, is a semiconductor that can be laid down as a thin film, an alternative to the crystalline silicon wafers that dominate most solar panels. First Solar builds its utility-scale Series 6 Plus modules on it, and the company rates each one at up to 480 watts.
The engineering problem is copper. A study by First Solar and the National Renewable Energy Laboratory found that CdTe cells have traditionally used copper to create the electric field that collects solar energy. Copper moves quickly through the layers of the cell, and that migration wears the cell down over its life.
CuRe, short for copper replacement, is First Solar's answer. It swaps copper for Group V elements, which the company regards as more stable, with the goal of slowing power loss over the long term. Earlier Series 6 modules are already in the field, including an array at the Penta Career Center campus in Perrysburg, Ohio.
Is Domestic Thin Film a Hedge Against Supply Bottlenecks?
Widmar's central claim is that every Gaffney module avoids reliance on crystalline silicon supply chains in countries such as China. Because CdTe panels do not use silicon wafers, that argument rests on the chemistry as much as on where the factory sits. He framed it against rising electricity demand in the United States.
Wood Mackenzie, the research firm, has pointed to a related risk for the wider market. A Foreign Entity of Concern, or FEOC, is a supplier whose ownership or location rules it out under US restrictions. Wood Mackenzie expects that sourcing components without FEOC ties could become a serious bottleneck over the next two to four years, given a large imbalance in the US clean energy transition.
First Solar leaders tie the investment to the current administration's trade policy and to the One Big Beautiful Bill Act, which backs President Donald Trump's goals of American energy dominance and affordability. That alignment is the company's own reading. How the policy plays out for module demand is a separate question.
Jobs and a Wider South Carolina Footprint
The company says the plant is on track to support nearly 700 jobs. About 500 positions have reportedly been filled already, which suggests roughly 200 hires remain as the second phase is built out.
Gaffney is not First Solar's first site in the state. The company already runs a distribution center in Duncan, Spartanburg County. It also has a long-running supply chain partnership with Inland Port Greer, an intermodal rail facility operated by the South Carolina Ports Authority. The new factory adds manufacturing to a logistics base that was already in place.
The national picture is larger. First Solar forecasts about 17 GW of US module manufacturing capacity by the end of this year, and says none of it will depend on Chinese crystalline silicon supply chains. Gaffney is a modest slice of that total, but it puts final assembly close to the customers the company is targeting.
| Asset | Location | Role | Status |
|---|---|---|---|
| Gaffney phase one | Gaffney, Cherokee County | Module finishing, 1.7 GW | Opened October 2026 |
| Gaffney full build | Gaffney, Cherokee County | Module finishing, 3.4 GW | Expected mid-2027 |
| Distribution center | Duncan, Spartanburg County | Distribution | Existing |
| Inland Port Greer | Greer | Intermodal rail partner, run by South Carolina Ports Authority | Longstanding partnership |
What could help or hurt the Gaffney build
The case for
- CuRe's replacement of copper with Group V elements targets the long-term degradation that the First Solar and NREL study links to copper diffusion.
- Wood Mackenzie's warning about FEOC-free sourcing suggests demand for modules with no Chinese crystalline silicon exposure could tighten over two to four years.
- Phase one opened less than a year after Gaffney was selected, according to Widmar, which supports the mid-2027 completion target.
The case against
- The second 1.7 GW phase and the mid-2027 date are company forecasts, not completed capacity.
- About 200 of the nearly 700 projected jobs still need to be filled.
- First Solar's case leans on current trade policy and the One Big Beautiful Bill Act, so a policy shift would weaken the rationale.
What to be careful about
- Delays to the second Gaffney phase would leave the plant at 1.7 GW instead of the 3.4 GW planned for mid-2027.
- The durability gains from CuRe are First Solar's own claims and depend on long-term field performance.
- The investment case is tied to the administration's trade policy and the One Big Beautiful Bill Act, which could change.
The bottom line
Gaffney gives First Solar a working 1.7 GW finishing line and a plan to double it to 3.4 GW by mid-2027. The case for the plant rests on two arguments. The first is technical: CuRe swaps copper for Group V elements to slow degradation in cadmium telluride cells. The second is political and commercial: modules with no link to Chinese crystalline silicon, at a time when Wood Mackenzie expects FEOC-free sourcing to tighten. The first phase has opened, while the second phase, the remaining hires and the 17 GW national forecast are still company projections. The milestones in December 2026 and mid-2027 will show whether the pace Widmar described holds up.
What to watch
- Watch whether First Solar reaches its forecast of about 17 GW of US module manufacturing capacity by the end of December 2026.
- Watch for the second phase at Gaffney, which would take the plant to 3.4 GW if it is completed on schedule in mid-2027.
- Watch whether Wood Mackenzie's warning about FEOC-free component sourcing becomes a real bottleneck within its two-to-four-year window; no specific date has been set.
Frequently asked questions
Where is First Solar's new South Carolina factory?
It is in Gaffney, Cherokee County. First Solar also runs a distribution center in Duncan, Spartanburg County, and works with Inland Port Greer, a rail facility run by the South Carolina Ports Authority.
How powerful are First Solar Series 6 Plus panels?
First Solar says each Series 6 Plus module produces up to 480 watts. The panels are thin-film cadmium telluride modules designed for utility-scale installations.
What is an FEOC in the solar industry?
A Foreign Entity of Concern is a supplier excluded because of its ownership or location under US rules. Wood Mackenzie expects that finding FEOC-free components could become a market bottleneck over the next two to four years.
How many jobs will the First Solar Gaffney plant create?
The company says the plant is on track to support nearly 700 jobs. About 500 have reportedly been filled already.