Blog
Kosinj Hydropower Tender Opens at EUR 480 Million
- November 20, 2026
- Posted by: Clean Energy Skills
- Category: hydropower

Estimated reading time: 6 minutes · Last updated:
Hrvatska Elektroprivreda (HEP), Croatia's state-owned power utility, has opened a public tender for the Kosinj hydropower system. It puts the estimated investment for the main civil works and equipment supply at EUR 480 million before tax. Companies have until 1 March 2027 to bid, and the winner gets 75 months to finish. The Kosinj hydropower works are one half of an upgrade to the 1960s-era Senj system on the Lika river. The other half is a new 375 MW plant, Senj 2. HEP says that once both are built, Croatia will have a 650 MW hydropower system, bigger than the 576 MW Zakučac plant. The tender moves the scheme from permits toward construction.
Key takeaways
- Tender value: HEP estimates the Kosinj civil works and equipment contract at EUR 480 million, excluding tax.
- Deadlines: Bids close on 1 March 2027, works are indicatively set to start on 1 July, and the contractor has 75 months to complete them.
- New capacity: The Senj 2 programme adds HPP Kosinj at 34.6 MW, HPP Senj 2 at 375 MW and 2 MW at HPP Sklope, for a stated total of 412 MW.
- System size: HEP says the finished system will reach 650 MW, more than the 576 MW Zakučac plant, with expected annual output of 132 GWh, mostly peak load energy.
- Existing role: In an average hydrological year, HES Senj covers roughly 5% of Croatia's electricity consumption.
Table of contents
- Key takeaways
- What the EUR 480 Million Kosinj Tender Actually Buys
- How Kosinj and Senj 2 Add Up to a 650 MW System
- Why HES Senj Already Matters to Croatian Power Supply
- A 75-Month Build After Years Without a New Croatian Plant
- What could speed or slow Kosinj
- What to be careful about
- Frequently asked questions
What the EUR 480 Million Kosinj Tender Actually Buys
HEP's call seeks one contractor to carry out the main civil engineering on HES Kosinj and to supply its equipment. The utility puts the estimated value of that contract at EUR 480 million, a figure that excludes tax. That number prices this tender. It is not necessarily the cost of the whole programme the tender belongs to.
The call gives three purposes for the project. Kosinj is meant to capture Lika river energy that the current scheme leaves unused. It is also meant to control flooding across the basin in the Kosinj valley, and to let the older plants downstream run more efficiently. HEP therefore presents it as an upgrade to HES Senj rather than as a standalone plant.
HEP says most of the groundwork is done. The location permit was granted in 2019. Since then the utility has completed the main designs and filed for every building permit the project needs. It has also settled most of the property and legal questions on the site. HEP presents these steps as meeting the conditions for construction to begin.
How Kosinj and Senj 2 Add Up to a 650 MW System
The Kosinj tender is one segment of a programme HEP calls the Senj 2 hydropower system. On the Kosinj side, the main unit is HPP Kosinj, rated at 34.6 MW. The other segment is HPP Senj 2, a 375 MW plant, and the programme also adds 2 MW to the existing HPP Sklope. HEP gives the combined new capacity as 412 MW.
Those additions sit on top of plants that already run. HES Senj today consists of HPP Sklope at 22.5 MW and HPP Senj at 216 MW, about 238.5 MW in total. Add the new units and the result is about 650 MW. That matches the total HEP cites for the finished system.
HEP says the completed system will outsize Zakučac, which has 576 MW of installed capacity, by about 74 MW. It names Zakučac as Croatia's largest hydropower plant. The utility expects annual output of 132 GWh, most of it peak load energy. Peak load energy is electricity supplied during the hours when demand on the grid is highest.
Why HES Senj Already Matters to Croatian Power Supply
HES Senj dates from the 1960s. It draws water from two rivers, the Lika and the Gacka, through its two plants. It is a significant asset for HEP. In an average hydrological year, it produces about 20% of the electricity from HEP's hydropower fleet.
Measured against everything HEP generates from all sources, the system supplies around 10% of output. Measured against national demand, it meets roughly 5% of Croatia's electricity consumption. Those shares make Senj one of the more important sites in HEP's portfolio. The Kosinj works are designed to raise its contribution by using water the current plants leave behind.
HEP's percentages describe an average year, so output in any given year depends on how much water the Lika and Gacka carry. That matters for how readers should treat the 132 GWh projection. It is an expectation tied to typical conditions, not a guaranteed annual figure.
A 75-Month Build After Years Without a New Croatian Plant
HEP started the second phase of the Senj scheme about six years ago. At that point the whole of Senj 2, at a combined 412 MW, was estimated at EUR 450 million. The new estimate of EUR 480 million covers only the Kosinj works and equipment. The two figures describe different scopes, so the change should not be read as a simple cost increase.
The schedule is long. Bids are due by 1 March 2027, and the call names 1 July as the indicative date for works to begin. The winning contractor then has 75 months to finish, which is a little over six years.
Vladimir Spasić of Balkan Green Energy News points out that Croatia's most recent hydropower commissioning was in 2010, when the 42.3 MW HPP Lešće came online. Kosinj and Senj 2 together would add almost ten times that capacity. They would also break a long gap in new hydropower construction in the country.
| Plant | Status | Capacity | Role |
|---|---|---|---|
| HPP Senj | Existing, 1960s | 216 MW | Core of HES Senj |
| HPP Sklope | Existing, 1960s | 22.5 MW plus 2 MW expansion | Part of HES Senj |
| HPP Kosinj | Planned, now tendered | 34.6 MW | Main unit of HES Kosinj |
| HPP Senj 2 | Planned | 375 MW | Second segment of Senj 2 |
| Zakučac | Existing | 576 MW | Named by HEP as the benchmark |
| HPP Lešće | Commissioned 2010 | 42.3 MW | Croatia's most recent hydro commissioning |
What could speed or slow Kosinj
The case for
- HEP says permits are applied for, designs are complete and most property issues are resolved, which removes common early-stage delays.
- The project expands an operating system that already supplies about 20% of HEP's hydropower output, rather than developing a new site.
- Flood regulation in the Kosinj valley gives the project a purpose beyond electricity generation.
The case against
- A 75-month construction window leaves a long period for cost or schedule changes.
- The EUR 480 million figure is an estimate. Actual bid prices are unknown until after 1 March 2027.
- The 375 MW HPP Senj 2, which provides most of the new capacity, is not covered by this tender.
What to be careful about
- Bids could come in above HEP's EUR 480 million estimate. The utility would then need to rescope the contract or accept a higher cost.
- Building permits have been applied for, but the call does not say all of them have been granted.
- The 650 MW total depends on HPP Senj 2 being delivered as well as Kosinj, and this tender does not secure that plant.
- The 132 GWh output projection assumes typical water flows on the Lika and Gacka.
The bottom line
The Kosinj tender turns a plan that has held permits since 2019 into a procurement with deadlines. HEP has spent the intervening years on designs, permit applications and land questions. It now needs a contractor to build the civil works and supply equipment for an estimated EUR 480 million. Several things are still open. One is how many firms bid by 1 March 2027 and how their prices compare with HEP's estimate. Another is whether the separate 375 MW Senj 2 plant follows on a similar schedule. If both segments are delivered, HEP says the result will be a 650 MW system on the Lika and Gacka that is larger than Zakučac.
What to watch
- Bids for the Kosinj civil works and equipment close on 1 March 2027, and the number of bidders and their prices will show whether the EUR 480 million estimate holds.
- HEP has set 1 July as the indicative start for works, following the March 2027 deadline; the published details do not state the year.
- Watch for HEP to name a contractor and for any separate procurement for the 375 MW HPP Senj 2; no date has been set for either.
Frequently asked questions
Who will build the Kosinj hydropower plant?
No contractor has been chosen yet. HEP is accepting bids until 1 March 2027 for the main civil works and equipment supply, a contract it values at EUR 480 million excluding tax.
When will the Kosinj hydropower system be finished?
HEP's call sets 1 July as the indicative start for works and gives the selected contractor 75 months to complete them. That puts the build at a little over six years from the start of construction.
What is the difference between HES Kosinj and HPP Senj 2?
They are the two segments of the Senj 2 hydropower system. HES Kosinj centres on the 34.6 MW HPP Kosinj and includes flood regulation in the Kosinj valley, while HPP Senj 2 is a separate 375 MW plant.
How much of Croatia's electricity does the Senj system supply?
In an average hydrological year, HES Senj covers roughly 5% of Croatia's electricity consumption. It also supplies around 10% of HEP's total generation.