Blog
NECEC outages spark dueling lawsuits with Hydro-Quebec
- September 11, 2026
- Posted by: Clean Energy Skills
- Category: hydropower

Estimated reading time: 5 minutes · Last updated:
NECEC outages prompted dueling federal lawsuits after New England’s new Canada-to-Massachusetts transmission line failed during periods of peak winter demand. Eversource, National Grid and Unitil say Hydro‑Quebec stopped deliveries and forced them to spend an extra $40 million on higher-cost generation; Hydro‑Quebec counters that the utilities owe it $50 million for power supplied in January and February. As first reported by CommonWealth Beacon, both complaints were filed this week in federal court in Boston and turn on whether the curtailments were a contract breach or a force majeure. The dispute raises immediate questions about the reliability of the New England Clean Energy Connect and the region’s ability to replace fossil-fired capacity with imported hydropower.
Hydro-Quebec is facing steep penalties for each day they are not providing power to Massachusetts, and we know they are working to resume power as quickly as possible.
Maria Hardiman, spokesperson, Executive Office of Energy and Environmental Affairs
Key takeaways
- Who sued whom: Eversource, National Grid and Unitil filed suit against Hydro‑Quebec in US District Court in Boston.
- Utilities' claimed cost: The utilities say Hydro‑Quebec’s interruptions cost them about $40 million in replacement energy.
- Hydro‑Quebec’s claim: Hydro‑Quebec is seeking $50 million from the utilities for energy delivered in January and February.
- Project scale: The New England Clean Energy Connect was intended to supply 20 percent of Massachusetts’s electricity.
Table of contents
- Key takeaways
- How the outages unfolded and why they matter
- What each court filing says and the sums at stake
- NECEC’s history: approvals, opposition and technical risk
- Policy and market implications for New England’s energy mix
- How the case could resolve and what would drive each outcome
- What to be careful about
- Frequently asked questions
How the outages unfolded and why they matter
The New England Clean Energy Connect (NECEC) began delivering power earlier this year and then experienced multiple pauses during high-demand periods. For all or parts of 12 days in late January and early February the line “went dark,” according to the utilities’ filing, and later in May and June the project was offline for about two weeks during an early-season heat wave. Those interruptions coincided with a regional spike in gas prices and a temporary return to heavier oil-fired generation, increasing costs and emissions as New England’s system strained.
The utilities contend the outages were imposed in a manner they describe as “discriminatory, discretionary, and non-transparent,” and that Hydro‑Quebec will “continue interrupting service” unless the court intervenes. Hydro‑Quebec says emergency reliability curtailments issued by its grid operator during extreme cold—and deaths and outages in Montreal tied to those weather events—meet the legal standard for force majeure, which it argues excuses nonperformance under the power contract.
What each court filing says and the sums at stake
The utilities’ complaint alleges that Hydro‑Quebec stopped sending power “in flagrant violation” of its contract, creating a 12-day shortfall and driving roughly $40 million in additional procurement costs for the utilities. Hydro‑Quebec’s response, filed the same day, asserts the utilities “have refused to pay” about $50 million for energy the company provided in January and February, and it frames the winter curtailments as force majeure. Both suits ask a federal judge to resolve breach and unpaid-bill claims and to decide who bears the financial fallout.
Those dollar figures—$40 million claimed by the utilities and $50 million sought by Hydro‑Quebec—represent the immediate financial stakes, but the litigation also threatens the long-term value of a project that required a 20-year power purchase agreement and a contentious approval process that included a $1 billion, 145-mile transmission corridor through Maine.
NECEC’s history: approvals, opposition and technical risk
NECEC’s path to operation was contested at multiple turns. Massachusetts regulators approved a 20-year power purchase agreement in 2018, and developers prevailed in a Maine court after a ballot measure sought to halt the $1 billion corridor. The line was designed to deliver up to the amount Central Maine Power — the project's developer — said would supply roughly 20 percent of the state’s electricity, creating a sizeable reliance on an international supplier and on a single long transmission path.
That dependence exposes the region to operational disruptions that are not purely local. When Quebec’s system issued emergency reliability curtailments during extreme cold—events that also caused power outages for more than 15,000 households in Montreal and led to two deaths—NECEC deliveries were affected. The contract’s force majeure language is now central: if the court accepts Hydro‑Quebec’s position, the company may be excused for some interruptions; if not, Hydro‑Quebec could face contractual penalties.
Policy and market implications for New England’s energy mix
The cases come as policymakers and utilities weigh how to meet emissions targets while keeping electricity affordable. Gov. Maura Healey hailed the line’s launch as a milestone in an “all-of-the-above” strategy, pointing to lower rates for ratepayers, but the litigation and repeated outages underscore the fragility of relying on a single, import-dependent source to displace gas and oil generation. The litigation also arrives amid federal and trade tensions with Canada that could complicate diplomatic or regulatory remedies.
For project developers and state regulators, the dispute highlights two levers: contract design and operational transparency. Longer-term planning depends on clear allocation of curtailment risk, routine public reporting when deliveries pause, and technical fixes where outages are attributed to equipment or grid-management issues rather than uncontrollable system emergencies.
| Item | Detail |
|---|---|
| Project | New England Clean Energy Connect (NECEC) |
| Intended share | 20 percent of Massachusetts electricity |
| Transmission corridor | 145 miles; $1 billion project cost cited |
| Contract term | 20-year power purchase agreement approved in 2018 |
| Utilities' claim | ~$40 million in replacement energy costs |
| Hydro‑Quebec claim | $50 million in unpaid energy charges |
How the case could resolve and what would drive each outcome
The case for
- A court ruling that recognizes Hydro‑Quebec’s force majeure defense would limit the company’s liability, reducing penalties and stabilising contract risk for other international suppliers.
- Settlement talks could allocate costs between the parties and include operational reforms, short-circuiting prolonged litigation and restoring shipments sooner.
The case against
- A finding against Hydro‑Quebec on breach could impose steep daily penalties and increase project costs for ratepayers, undermining the economic case for NECEC.
- If the litigation drags on, utilities may rely longer on oil and gas peaker units, raising emissions and consumer bills and weakening political support for long transmission imports.
What to be careful about
- A court ruling for Hydro‑Quebec could reduce enforceability of similar force majeure defenses in long-term import contracts.
- Extended litigation may force heavier short-term use of oil-fired generation, increasing both emissions and fuel costs in New England.
The bottom line
The dueling suits over NECEC turn a technical and operational dispute into a legal test of who bears shortage risk in long-term cross-border energy contracts. The utilities point to a roughly $40 million hit in replacement purchases; Hydro‑Quebec counters with a $50 million billing claim and invokes force majeure tied to extreme weather. A court decision or a negotiated settlement will determine whether NECEC remains a cornerstone of Massachusetts’ decarbonisation plan or becomes an example of the limits of relying on a single international supply route.
What to watch
- Watch for the US District Court in Boston to schedule initial hearings; no date has been set.
- Watch whether the parties file a settlement notice or request for mediation; no date has been set.
Frequently asked questions
What claims did the Massachusetts utilities make in court?
Eversource, National Grid and Unitil allege Hydro‑Quebec halted deliveries in a way they call a breach and that those interruptions forced roughly $40 million in higher-cost energy purchases.
What is Hydro‑Quebec seeking from the utilities?
Hydro‑Quebec filed its own federal suit demanding about $50 million that it says the utilities have “refused to pay” for energy supplied in January and February.
How much of Massachusetts’ electricity was NECEC intended to supply?
Developers and officials have said NECEC was intended to supply about 20 percent of Massachusetts’s electricity under a 20-year power purchase agreement approved in 2018.
Related reading