Blog
CNE Approves Mexico Solar Permits Worth US$750M for 649MW
- November 11, 2026
- Posted by: Clean Energy Skills
- Category: Solar Energy

Estimated reading time: 6 minutes · Last updated:
Six Mexico solar permits carrying a combined US$750 million in private investment have been approved by the CNE under the Privados II call for proposals. Together the plants are designed to deliver 649MW of net capacity to the National Power System (SEN), with 751MWac installed and an expected 1,881GWh of output a year. Every project must include battery storage, and all six are scheduled to reach commercial operation in 2028 and 2029. Three developers share the awards: Green Park Energy, Ammper Generación and Viva El Sol. The approvals come as nearshoring lifts industrial electricity demand across Mexico. Building the plants now looks like the easier half of the job, because the transmission network that has to carry their output is already under strain.
Key takeaways
- Approval: The CNE approved six solar generation permits worth a combined US$750 million in private investment under the Privados II call for proposals.
- Capacity: The plants add 649MW of net capacity and 751MWac installed, with expected generation of 1,881GWh a year and commercial operation due in 2028 and 2029.
- Winners: Green Park Energy, a Cox subsidiary, won three permits, Invex Controladora's Ammper Generación won two including the Antares project in Tlaxcala, and Viva El Sol won one in Coahuila.
- Selection: Of 57 proposals submitted, 31 qualified and just six cleared every compliance and technical test, roughly 11 percent of all submissions.
- Storage: Mandatory battery systems across the six projects total 204MW and about 628MWh, around three hours of discharge at full power.
Table of contents
- Key takeaways
- What 649MW of Net Capacity Adds to Mexico's Grid
- Which Developers Won and Where They Will Build
- Why Only Six of 57 Proposals Made It Through
- Storage Is a Condition of the Permits, Not an Option
- Transmission Is the Harder Problem
- What could help or hold back the six projects
- What to be careful about
- Frequently asked questions
What 649MW of Net Capacity Adds to Mexico's Grid
The headline figure is 649MW of net capacity, the amount the six plants are meant to feed into the SEN. Installed alternating current capacity is higher, at 751MWac. That leaves a gap of roughly 102MW between what will be built and what counts as net, and the reason for the difference was not set out with the approval.
Expected annual generation is 1,881GWh. Capacity factor is the share of its theoretical maximum output a plant actually produces over a year. Measured against the 751MWac installed base, these projects would run at a capacity factor of about 29 percent.
The investment works out to roughly US$1.16 million per MW of net capacity, or about US$125 million per permit on average. Those are blended figures, because the US$750 million was not broken down project by project. None of this electricity is expected on the grid before 2028, and part of it is scheduled for 2029.
Which Developers Won and Where They Will Build
Green Park Energy, a subsidiary of Cox, took three of the six permits. Its sites are in Aguascalientes, Jalisco and Guanajuato, so half of the round went to a single company.
Ammper Generación, part of Invex Controladora, won two permits. The one identified by name is the Antares project in Tlaxcala, and the location of Ammper's second site was not specified. Viva El Sol received the remaining permit, for a project in Coahuila.
The split of the 649MW between the three developers was not published alongside the permits. A count of permits therefore says nothing about which company will own the most generation. That breakdown matters for anyone tracking how concentrated private solar ownership is becoming under the new rules, and it is the first detail worth requesting from the companies or the regulator.
Why Only Six of 57 Proposals Made It Through
Privados II is the second call for proposals through which private developers compete for generation permits. It drew 57 submissions. Thirty-one of those qualified, and six passed every compliance and technical requirement. That is about 11 percent of all bids and about 19 percent of the qualified ones.
The arithmetic shows that money was not what held most applicants back. Twenty-five qualified proposals were still turned away. The binding filter was the technical and compliance test, and the focus now shifts to whether the six winners can build on time.
The round sits inside a wider federal plan. That plan directs more than two-thirds of energy-related investment allocations through 2030 toward generation, from both the state and private developers. Privados II is one channel for the private share, and six permits with 649MW of net capacity is its latest output.
Storage Is a Condition of the Permits, Not an Option
Each project must include a battery energy storage system (BESS), meaning banks of batteries that charge when output is high and discharge when it falls. Across the six sites the systems total 204MW of power and about 628MWh of energy.
Dividing energy by power gives a discharge duration of roughly three hours at full output. The battery fleet's power rating equals about 31 percent of the plants' net capacity. The aim is to smooth solar output, which drops with cloud cover and disappears after sunset, and to make the new supply more dependable for industrial users.
Most of the new capacity is concentrated in two regions. The Western Region takes 350MW and the Eastern Region 289MW. The Northeastern Region receives just 10MW, which adds up to the 649MW total.
Transmission Is the Harder Problem
New generation does little if the wires cannot carry it. Industrial hubs drawing heavy nearshoring investment are already testing substations and transmission lines. These 649MW will have to be matched with CFE's grid investment and modernisation plans if the power is to reach factories.
For companies weighing a Mexican site, the reliability of supply has become a deciding factor. Manufacturing losses during major outages have shown what an unreliable grid costs. A permit approved in 2026 for a plant energised in 2028 or 2029 is a promise of capacity, not a guarantee of delivery to a specific industrial park.
Privados II shows that private capital is available for Mexican solar. Whether the grid can absorb what that capital builds depends on work the CFE controls, not the developers.
| Developer | Parent | Permits | States |
|---|---|---|---|
| Green Park Energy | Cox | 3 | Aguascalientes, Jalisco, Guanajuato |
| Ammper Generación | Invex Controladora | 2 | Tlaxcala (Antares); second site not specified |
| Viva El Sol | Not stated | 1 | Coahuila |
What could help or hold back the six projects
The case for
- Mandatory batteries of 204MW and about 628MWh give the plants roughly three hours of shiftable output, which supports evening supply.
- Generation receives more than two-thirds of energy-related investment allocations through 2030 under the federal plan, giving private developers a policy backdrop.
- A strict filter that admitted six of 57 proposals means the winners have already cleared full compliance and technical review.
The case against
- Strained substations and transmission lines in nearshoring hubs could limit how much of the 649MW reaches industrial users.
- Delivery depends on CFE grid investments that the developers do not control.
- Commercial operation is not due until 2028 and 2029, leaving a long build window in which timelines can slip.
What to be careful about
- Grid connection: if CFE transmission upgrades lag, completed plants could be constrained in how much power they deliver.
- Schedule slippage: the projects must move from permit to operation over a period running into 2029.
- Opacity: the per-project investment and capacity split has not been published, making progress hard to track against commitments.
The bottom line
The CNE's Privados II approvals put US$750 million of private money behind six solar plants. They promise 649MW of net capacity, 1,881GWh a year and 204MW of mandatory battery storage, starting in 2028. The round was demanding: six winners from 57 proposals, with 25 qualified bids left out. That suggests the regulator is choosing carefully rather than struggling to attract capital. The open questions are the ones the announcement left unanswered: how the capacity splits between Green Park Energy, Ammper Generación and Viva El Sol, and whether CFE's grid work keeps pace. A permit counts for little without a transmission line able to carry the power, and in Mexico's nearshoring hubs those lines are already stretched.
What to watch
- Watch for the first of the six plants to reach commercial operation, scheduled for 2028.
- Watch for the remaining projects to enter service in 2029, the latest date set for the round.
- Watch for CFE transmission and substation work in the Western and Eastern regions, which take most of the new capacity; no completion dates have been set.
Frequently asked questions
How many companies applied in Mexico's Privados II solar round?
Privados II drew 57 submissions, of which 31 qualified. Only six met every compliance and technical requirement and received permits, about 11 percent of the total.
When will the new Mexican solar plants start producing power?
Commercial operation is scheduled for 2028 and 2029. Until then the 649MW of net capacity and 1,881GWh of expected annual output exist only on paper.
How much battery storage comes with the Privados II solar projects?
The six projects must include battery systems totalling 204MW and about 628MWh. That allows roughly three hours of discharge at full power.
Which regions of Mexico get the new solar capacity?
The Western Region receives 350MW, the Eastern Region 289MW and the Northeastern Region 10MW. Named states include Aguascalientes, Jalisco, Guanajuato, Tlaxcala and Coahuila.