South Korea Hydrogen Tenders Raise Non-Price Weight to 50%
- November 7, 2026
- Posted by: Clean Energy Skills
- Category: Hydrogen Energy

Estimated reading time: 6 minutes · Last updated:
South Korea's Ministry of Climate, Energy and Environment (MCEE) will give non-price criteria half the weight in its clean hydrogen power generation tenders, up from 40%. It is also shutting coal-ammonia co-firing projects out of the auctions. Bids will go through a two-step test. The first screen looks only at non-price factors, and the final score is split evenly between price and everything else. The change links the South Korea hydrogen tenders to the government's aim of ending coal-fired generation by 2040. The clean market offers 500 gigawatt-hours a year under 15-year contracts, with winners due around June 2027. A separate general hydrogen market, sized at 930 GWh a year for its 2026 round, picks its preferred bidders around December 2026.
Key takeaways
- Weighting shift: The MCEE is lifting the share of non-price criteria in South Korea's clean hydrogen power tenders from 40% to 50%, putting price and non-price factors on equal footing.
- Two-stage screen: A first round judged on non-price criteria alone keeps bids covering up to 1.5 times the target capacity, and only those bids are then scored on price.
- Coal-ammonia excluded: Coal-ammonia co-firing projects are barred from the clean hydrogen tenders, in line with South Korea's goal of phasing out coal power by 2040.
- Clean market terms: The clean hydrogen market targets 500 GWh a year on 15-year contracts, with power flowing by 2030 and preferred bidders chosen around June 2027.
- General market terms: The general hydrogen market offers 930 GWh a year in 2026 on 20-year contracts, adds a carbon capture assessment indicator, and selects bidders around December 2026.
Table of contents
- Key takeaways
- How the Two-Stage Scoring Filters Out Cheap Bids
- Why Coal-Ammonia Projects Are Out and Which Fuels Qualify
- What the Clean Hydrogen Market Offers Winning Bidders
- How the General Hydrogen Market Differs
- What could help or hinder the new tender design
- What to be careful about
- Frequently asked questions
How the Two-Stage Scoring Filters Out Cheap Bids
The first round of assessment ignores price entirely. The MCEE will judge bids only on non-price criteria. It will keep enough of them to cover up to 1.5 times the capacity being sought. Whatever survives moves to a second, comprehensive round, where price and non-price factors each make up 50% of the score.
The practical effect is that a low bid cannot win on cost alone. A project has to clear the non-price screen before its price is looked at. Even then, cost counts for only half of the final mark. Under the previous split, non-price factors carried 40%, which left price with the larger share. The change amounts to a shift of 10 percentage points toward non-price factors.
The ministry names four non-price criteria. They are contribution to industry and the economy, reductions in greenhouse gas emissions, the clean hydrogen utilisation grade, and security of fuel supply. Together they let the government reward projects for what they do for domestic industry and emissions, not just for how cheaply they can generate.
Why Coal-Ammonia Projects Are Out and Which Fuels Qualify
Coal-ammonia co-firing means burning ammonia alongside coal in an existing coal-fired plant. That approach lowers a plant's emissions but keeps it running on coal. The MCEE is excluding such projects from the clean hydrogen tenders. It ties that decision to the government's target of phasing out coal-fired power generation by 2040.
Eligibility also depends on the fuel itself. Only facilities burning fuel that meets South Korea's clean hydrogen certification standards can take part. Those standards cap emissions at 4 kg of carbon dioxide equivalent for every kilogram of hydrogen produced. A carbon dioxide equivalent is a common unit that expresses different greenhouse gases in terms of the warming effect of carbon dioxide.
The two rules work together. The certification ceiling governs how the hydrogen is made, and the coal exclusion governs where it is burned. A bidder has to satisfy both before the scoring begins.
What the Clean Hydrogen Market Offers Winning Bidders
The clean hydrogen power generation market is sized at 500 GWh of electricity a year. Contracts run for 15 years. Winners get a three-year window to prepare their projects, and generation has to start by 2030. The MCEE expects to name preferred bidders around June 2027.
The ministry has also built in some tolerance for slippage. Penalties for late projects will not apply until a grace period of up to three years has passed. The government says the allowance reflects how long it takes to build hydrogen co-firing plants and full-conversion facilities. Co-firing here means burning hydrogen together with another fuel, while a full-conversion facility switches a plant over to hydrogen entirely.
That grace period matters because the timeline is tight. A three-year preparation window followed by construction leaves little room if equipment or fuel supply runs late. The extra years soften that risk without changing the 2030 start target.
How the General Hydrogen Market Differs
Alongside the clean market, South Korea runs a general hydrogen power generation market. It is meant to encourage distributed power sources, meaning smaller generators spread across the grid rather than large central plants. Its 2026 round is sized at 930 GWh a year, nearly twice the clean market's volume, on 20-year contracts.
The timetable is shorter. Projects get two years of preparation and must generate power by 2029. Preferred bidders are due to be chosen around December 2026, after an assessment covering price and non-price criteria. These include effects on the power grid and contributions to industry and the economy.
The general market is also tightening its environmental tests. It adds a new indicator that scores bidders on their plans for carbon dioxide capture, utilisation and storage, the practice of trapping emissions and either reusing them or locking them away. Dedicated hydrogen auctions are spreading beyond Korea as well. In Germany, Gemini has replaced Heimdal in the country's window of the European Hydrogen Bank.
| Market | Annual volume | Contract length | Preparation period | Generation start | Preferred bidders |
|---|---|---|---|---|---|
| Clean hydrogen | 500 GWh | 15 years | 3 years | By 2030 | Around June 2027 |
| General hydrogen | 930 GWh (2026 round) | 20 years | 2 years | By 2029 | Around December 2026 |
What could help or hinder the new tender design
The case for
- The non-price first stage rewards bids for industrial contribution, emissions cuts and fuel supply security before cost is considered.
- Excluding coal-ammonia co-firing keeps the tenders consistent with the 2040 coal phase-out goal.
- A grace period of up to three years before delay penalties gives builders of co-firing and full-conversion plants room to finish.
The case against
- If higher-cost bids score well on non-price criteria, the auctions could deliver hydrogen power at a higher price than a price-led design.
- Owners of coal plants lose co-firing with ammonia as a route into the clean hydrogen market.
- The 4 kg carbon dioxide equivalent ceiling limits which hydrogen supplies can be used, which could narrow the field of eligible bidders.
What to be careful about
- Projects that miss the 2030 start date for the clean market, or the 2029 date for the general market, face penalties once the grace period of up to three years runs out.
- Criteria such as contribution to industry and the economy are not pure numbers, so the non-price screen could lead to disputes over how bids were ranked.
- Developers that prepared coal-ammonia co-firing proposals now have no place in the clean hydrogen tenders.
The bottom line
South Korea is redesigning its clean hydrogen auctions so that price no longer leads. Non-price criteria rise from 40% to 50% of the score, and a non-price-only first round decides which bids get a final assessment at all. Coal-ammonia co-firing is excluded, and fuel must meet a 4 kg carbon dioxide equivalent ceiling. The result is a market that rewards industrial contribution and emissions performance, at a possible cost to price competition. The first real tests come soon. The general market names its bidders around December 2026, and the clean market follows around June 2027. Whether developers can then meet start dates of 2029 and 2030 will show if the three-year grace period was generous enough.
What to watch
- Watch for the general hydrogen market's preferred bidders, which the MCEE expects to select around December 2026, the first round to include the carbon capture indicator.
- Watch for the clean hydrogen market's preferred bidders around June 2027, the first test of the 50-50 price and non-price scoring.
- Watch whether general market projects begin generating by the 2029 deadline and clean market projects by 2030, before the delay grace period of up to three years expires.
Frequently asked questions
What hydrogen counts as clean in South Korea's tenders?
Only fuel meeting South Korea's clean hydrogen certification standards is accepted. Those standards allow no more than 4 kg of carbon dioxide equivalent per kilogram of hydrogen. Facilities using fuel above that ceiling cannot bid.
What happens if a South Korean hydrogen power project is late?
The MCEE will allow a grace period of up to three years before delay penalties apply. It says the allowance reflects the construction time needed for hydrogen co-firing and full-conversion facilities. Clean market projects are still expected to generate by 2030.
When will South Korea choose winners in its hydrogen auctions?
Preferred bidders in the general hydrogen market are due around December 2026. Winners in the clean hydrogen market are expected around June 2027. Both follow assessments that combine price and non-price criteria.