Nepal Hydropower IPOs Could Need 50 Percent Construction
- November 16, 2026
- Posted by: Clean Energy Skills
- Category: hydropower

Estimated reading time: 5 minutes · Last updated:
Hydropower companies in Nepal could sell shares to the public while their plants are still being built, but only once at least 50 percent of the physical work is certified complete. That threshold sits in a draft ordinance the government is preparing. The ordinance would amend several of the country's investment and infrastructure laws, the Securities Act 2006 among them. Under the draft, a hydropower IPO application could not be turned down simply because the project has not yet begun commercial production. The provision answers a stricter draft rule from the Securities Board of Nepal, which would have required a record of continuous business operation before any public offering, as first reported by The Kathmandu Post. Hydropower promoters had objected to that requirement.
Key takeaways
- The 50 percent threshold: Nepal's draft ordinance would let a hydropower company apply for an IPO once its project reaches at least 50 percent certified physical progress.
- No power output needed: A hydropower IPO application could not be refused only because the plant has yet to start commercial production.
- Securities Act 2006: The ordinance bundles amendments to several Nepal investment and infrastructure laws, including the Securities Act 2006.
- The rule it answers: The Securities Board of Nepal's draft 2026 eligibility guidelines proposed continuous business operation as a precondition for public offerings, which hydropower promoters opposed.
Table of contents
- Key takeaways
- What the 50 Percent Construction Threshold Requires
- Why the Securities Board Draft Worried Hydropower Developers
- Share Buyers Would Be Backing Half-Built Plants
- What Is Still Pending Before the Rule Takes Effect
- Arguments for and against the threshold
- What to be careful about
- Frequently asked questions
What the 50 Percent Construction Threshold Requires
An initial public offering, or IPO, is the first sale of a company's shares to the general public. Under Nepal's draft ordinance, a company building a hydropower project becomes eligible to apply for one when the project reaches at least 50 percent certified physical progress. It must also satisfy the other conditions that apply to any public issuance.
The draft adds a protection for applicants. An application could not be rejected on the single ground that the plant is not yet in commercial production. Put plainly, a developer would not need to be generating electricity to raise equity from the public, but it would have to show the build is at least halfway done.
That makes physical progress, rather than operating history, the test for hydropower firms with projects under construction. It is a measurable standard tied to what exists on site, which is a different question from whether a business has a track record of running.
Why the Securities Board Draft Worried Hydropower Developers
The ordinance follows a separate move by the Securities Board of Nepal. In its draft 2026 Guidelines on General Eligibility for Public Issuance, the board suggested a company should have a record of continuous business operation before it could offer shares to the public.
For a hydropower developer, that standard would have kept the IPO route closed until a plant was running. Promoters objected, arguing that the rule would shut them out of public share sales during construction, which is the phase when their demand for money is greatest.
The draft ordinance settles the clash by writing a distinct threshold for hydropower firms whose projects are still being built. Instead of waiting for operations to begin, they would point to certified progress on the ground. The test shifts from how long a company has been in business to how much of its plant has been completed.
Share Buyers Would Be Backing Half-Built Plants
The change matters to anyone considering a hydropower IPO in Nepal. Shares issued under the 50 percent rule could come from companies that are not yet selling any electricity. Up to half of the physical work could still lie ahead when the public buys in.
The threshold is a floor, not a guarantee. Certified progress shows how much has been built; it says nothing about when the plant will start producing or what it will earn. The ordinance also keeps the general requirements for public issuance in place, so the 50 percent mark is one condition among several.
For promoters, the trade-off runs the other way. They would reach public capital earlier than the Securities Board draft would permit, at the price of proving construction progress first.
What Is Still Pending Before the Rule Takes Effect
None of this is law yet. The government is preparing to issue the ordinance, but no issuance date has been given, and the text remains a draft that could change before it is final.
The Securities Board's guidelines are also still in draft form. Whether the board revises its continuous-operation test, or leaves it in place for other sectors while hydropower follows the ordinance's threshold, has not been stated.
Two practical details also remain unclear in the provision as described so far: who certifies physical progress, and which other issuance requirements apply. The hydropower clause is also one piece of a wider package of amendments to investment and infrastructure laws, so its final shape depends on how the whole bundle is settled.
| Instrument | Issued by | Condition for an IPO | Status |
|---|---|---|---|
| Draft 2026 Guidelines on General Eligibility for Public Issuance | Securities Board of Nepal | Continuous business operation before a public offering | Draft |
| Draft ordinance amending investment and infrastructure laws | Government of Nepal | At least 50 percent certified physical progress for hydropower projects under construction | Draft, not yet issued |
Arguments for and against the threshold
The case for
- Developers could raise public equity during construction instead of waiting for commercial production.
- A certified 50 percent progress test ties eligibility to measurable work on site.
- An application cannot be rejected solely for lack of commercial production, removing one ground for refusal.
The case against
- Public shareholders could be buying into projects with up to half of the physical work still unfinished.
- The certifying body and the measurement method are not specified in the provision as described.
- The ordinance and the Securities Board guidelines are both drafts, leaving the final rule uncertain.
What to be careful about
- Companies listing under the 50 percent rule may not yet be generating electricity, so share buyers would carry construction-stage exposure.
- The draft ordinance could change before issuance, altering or removing the 50 percent threshold.
- The relationship between the ordinance and the Securities Board of Nepal's continuous-operation proposal has not been clarified.
The bottom line
Nepal's government is choosing between two ideas of readiness. The Securities Board of Nepal's draft would judge companies by a track record of continuous operation; the draft ordinance would judge hydropower developers by how much of their plant already stands. Setting the bar at 50 percent certified physical progress gives promoters a path to public capital during construction, which is what they said they needed, while still demanding evidence that a project is real and advancing. The open questions are practical ones: who certifies the progress, what other issuance conditions apply, and when the ordinance is actually issued. The threshold remains a proposal rather than a rule while those questions stay unanswered.
What to watch
- Watch for the government to formally issue the ordinance amending the investment and infrastructure laws; no date has been set.
- Watch for the Securities Board of Nepal to finalise its Guidelines on General Eligibility for Public Issuance and say how they treat hydropower companies; no date has been given.
Frequently asked questions
Can a hydropower company in Nepal hold an IPO before it produces electricity?
Under the government's draft ordinance, yes, provided the project has reached at least 50 percent certified physical progress and meets the other public issuance conditions. The ordinance has not yet been issued.
What did the Securities Board of Nepal propose for IPO eligibility?
In its draft 2026 Guidelines on General Eligibility for Public Issuance, the Securities Board of Nepal suggested companies should have a record of continuous business operation before making a public offering. Hydropower promoters objected because that would block share sales during construction.
Which law covers share issuance in the draft ordinance?
The ordinance would amend several Nepal laws on investment and infrastructure, and the Securities Act 2006 is among them. The hydropower IPO threshold is one provision within that wider package.